China Mobile YRD (Wuhu) Data Centre (中国移动长三角(芜湖)数据中心)
Wuhu, Anhui, China · Wuhu market · location approximate to district level
China Mobile YRD (Wuhu) Data Centre (中国移动长三角(芜湖)数据中心) is a data center project in Wuhu, China, operated by China Mobile Anhui (中国移动安徽公司). It is under construction. The operator has not published an IT load figure. It is planned for 7,815 racks. ArusGrid does not convert racks into MW.
Latest change on record: entered the record as under construction on 17 October 2024. Record last checked against its sources on 22 October 2026.
✓ Land secured✓ Power arranged✓ Approvals granted○ Money committed○ Tenant or own use✓ Builder appointed✓ Construction started
Next gate to watch: Money committed.
Your call. Will it be built?
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.
Wuhu holds 6 active projects with 298 MW of planned IT load between them, and China Mobile YRD (Wuhu) Data Centre (中国移动长三角(芜湖)数据中心) has no published figure so it sits outside that ranking. Of those, 2 are operational and expanding and 4 are under construction. No third party publishes a colocation vacancy rate for Wuhu, and ArusGrid does not estimate one.
China Mobile has 11 others in China tracked by ArusGrid, including China Mobile Zhongwei Data Center, Park B, China Mobile (Gansu Qingyang) Data Center and China Mobile Hohhot Data Center. It sits on the Jiangbei New Area industrial concentration zone (江北新区产业集中区) campus. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The stage was recorded as under construction on 17 October 2024. The money on record is CN¥6bn as of October 2024, the announced investment.
The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 8 public sources for this project, the latest dated 19 September 2026, and last checked the record on 22 October 2026.
How well evidenced is it
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusLikely
Planned for 22 EFLOPS of compute with 1,278 AI racks at 40kW each (Oct 2024).
Access to AI chips
GradeLicence required for a party
A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.
US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo
Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source
Phases
3 Grade A data centre buildings, 1,278 AI racks at 40kW and 6,537 general racks at 7kW · Under constructionSize not published
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.
Money at this site
Announced investment, 2024-10CN¥6bn
The figure covers the whole campus.
Colocation price per kW of IT load per month
No colocation price applies to this product (retail interconnection, no colocation price applies).
Project team
Design and build contractor中国建筑第八工程局有限公司 (中建八局) · Apr 2025 Reportedsource ↗
Phase 2 general contractor jointly with 中国移动通信集团设计院有限公司. Phase 2 is about 33,000 sqm: a five-storey steel-frame data hall, a diesel generator platform and a 110kV substation, plus external works.
Design and build contractor中国移动通信集团设计院有限公司 · Apr 2025 Reportedsource ↗
Joint general contractor with 中建八局 for phase 2.
Mechanical and electrical works易事特 (East Group) · Mar 2026 Reportedsource ↗
Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.