Reliance Jamnagar Meta build-to-suit is a data center project in Jamnagar, India, operated by Reliance Intelligence. It has been announced and has not yet reached the land or permitting stage. It is planned for 168 MW of IT load.
Latest change on record: entered the record as announced on 10 June 2026. Record last checked against its sources on 21 October 2026.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How India approves, powers and taxes data centers is on Data center rules in India.
Gujarat holds 3 active projects with 538 MW of planned IT load between them, and Reliance Jamnagar Meta build-to-suit ranks second by planned capacity. Of those, 3 are announced only. No third party publishes a colocation vacancy rate for Gujarat, and ArusGrid does not estimate one.
Reliance has 1 other in India tracked by ArusGrid, including Reliance Intelligence Jamnagar AI data centre (phase 1). It sits on the Reliance Jamnagar AI campus alongside Reliance Intelligence Jamnagar AI data centre (phase 1). Named funding comes from Reliance Industries on the equity side. The named user of the compute is Meta (confirmed).
The stage was recorded as announced only on 10 June 2026. Power comes from Reliance Industries Ltd (reported, unconfirmed).
The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 2 public sources for this project, the latest dated 11 June 2026, and last checked the record on 21 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Meta-leased AI training and inference facility; no GPU count disclosed.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
168 MW · Full facility, 168MW initial phase with options to scale · as of 2026-06-10
Meta's own newsroom says Reliance builds and owns the Jamnagar facility and Meta leases capacity, 168MW initial phase, covering energy and water costs; Meta separately contracted about 1GW of renewables from CleanMax and Fourth Partner Energy.
Source · Meta Partners With Reliance on AI-Enabled Data Center in India (Meta Newsroom, 2026-06-10)
Source · Meta signs first AI data center deal in India with Reliance (TechCrunch, 2026-06-10)
No figure has been announced. This range is 168 MW of planned IT load times a published benchmark of US$6.64 per watt for Mumbai, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.
Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.
An own-use build. No colocation price applies.
All projects in Gujarat · All projects in India · All Reliance projects · All projects announced only · Data center rules in India · Full directory