ArusGridProject
Directory › Vietnam › Hanoi metro › VNPT IDC Hoa Lac

VNPT IDC Hoa Lac data center

Hoa Lac, Hanoi, Vietnam · Hanoi metro market · location approximate to district level

VNPT IDC Hoa Lac is a data center project in Hoa Lac, Vietnam, operated by VNPT (VNPT IDC). It is operational. The operator has not published a capacity figure, and ArusGrid does not estimate one.

Record last checked against its sources on 11 September 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
VNPT (VNPT IDC)
Telco
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Vietnam approves, powers and taxes data centers is on Data center rules in Vietnam.

Where it sits

Hanoi metro holds 6 active projects with 110 MW of planned IT load between them, and VNPT IDC Hoa Lac has no published figure so it sits outside that ranking. Of those, 3 are operational, 1 is under construction, 1 is at the land and permitting stage and 1 is announced only. No third party publishes a colocation vacancy rate for Hanoi metro, and ArusGrid does not estimate one.

It is the only VNPT project ArusGrid tracks. It sits on the Hoa Lac Hi-Tech Park alongside G-Campus Hoa Lac (High-Tech & Data Centre Complex), National Data Center No.1 and Viettel IDC Hoa Lac. Named funding comes from VNPT on the equity side. No user of the capacity is on the public record as of 2026-10-02, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

Grid power for a large industrial user in Vietnam costs about US$0.073 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Vietnam, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:1), no named authorisation found”. ArusGrid holds 4 public sources for this project, the latest dated 4 March 2026, and last checked the record on 11 September 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

Radian Arc and Blacknut launched a live GPU cloud inside this facility (DCD, 2026-03-04), serving cloud gaming and inference. An actual GPU deployment, not an inference from design or scale.

Access to AI chips

GradeNo public signal

Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required as enforced (Country Group D:1), no named authorisation found · Licence required as enforced (Country Group D:1), no named authorisation found (2026-09-27) source

Who is behind it

OperatorVNPT (VNPT IDC) · Telco
Funder, EquityVNPT

Who uses the compute

Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Colocation price per kW of IT load per month

No published price band exists for Vietnam, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-09-11

  1. vnpt.com.vn
  2. datacenterdynamics.com
  3. baxtel.com
  4. Radian Arc and Blacknut launch GPU cloud in Vietnam (DatacenterDynamics, 2026-03-04)

Same campus, Hoa Lac Hi-Tech Park

More in Hanoi metro

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.