ArusGridProject
Directory › China › Horinger and Hohhot › Bank of Communications Horinger New Area Data Center (交通银行和林格尔新区数据中心)

Bank of Communications Horinger New Area Data Center (交通银行和林格尔新区数据中心)

Horinger New Area, Hohhot, Inner Mongolia, China · Horinger and Hohhot market · location approximate to district level

Also listed as 交通银行和林格尔数据中心 and BoCom Horinger.

Bank of Communications Horinger New Area Data Center (交通银行和林格尔新区数据中心) is a data center project in Horinger New Area, Hohhot, China, operated by Bank of Communications (交通银行). It is under construction. The operator has not published an IT load figure. It is planned for 10,000 racks. ArusGrid does not convert racks into MW.

Latest change on record: moved to under construction on 8 August 2024. Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Bank of Communications (交通银行)
Local developer
AI workloads
Unlikely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted○ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

Next gate to watch: Money committed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.

Where it sits

Horinger and Hohhot holds 10 active projects with 298 MW of planned IT load between them, and Bank of Communications Horinger New Area Data Center (交通银行和林格尔新区数据中心) has no published figure so it sits outside that ranking. Of those, 3 are operational, 1 is operational and expanding, 1 is under construction, 2 are at the land and permitting stage and 3 are announced only. No third party publishes a colocation vacancy rate for Horinger and Hohhot, and ArusGrid does not estimate one.

Bank of Communications has 1 other in China tracked by ArusGrid, including Bank of Communications Gui'an Data Center. The named user of the compute is Bank of Communications (confirmed).

The dated record runs from announced only on 16 March 2023 to under construction on 8 August 2024. The money on record is CN¥5bn as of August 2024, the announced investment. Power comes from 交通银行股份有限公司内蒙古自治区分行 (own phase 1 110kV substation) through a dedicated substation at 110 kV.

The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 11 public sources for this project, the latest dated 23 March 2026, and last checked the record on 22 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusUnlikely

A bank's own-use data centre. No AI purpose is stated.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source

Phases

Phase 1 · Under constructionSize not published

Stage history

2023-03-16Announced · hlgena.huhhot.gov.cn
2024-08-08Under construction · idcquan.com

Who is behind it

OperatorBank of Communications (交通银行) · Local developer

Who uses the compute

Own use · enterpriseBank of Communications · confirmed

as of 2024-08-08

The bank's own data centre.

Source · 规划超1万机架 交通银行和林格尔新区数据中心开工 (中国IDC圈, 2024-08-08)

Money at this site

Announced investment, 2024-08CN¥5bn

The figure covers the whole campus.

Colocation price per kW of IT load per month

No published price band exists for China, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Engineering consultant中讯邮电咨询设计院有限公司 · CNY 4.22m · Jul 2025 · shortlisted Confirmed source ↗
Machine room testing and certification services for phase 1. Planned completion 27 Jan 2026.
Main contractor中国建筑第八工程局有限公司 (China Construction Eighth Engineering Division) · Mar 2025 Reported source ↗
Phase 1 construction of the Horinger data centre
Fit-out contractor天津恋日雅光照明工程有限公司 · CNY 3.14m · Jun 2025 Confirmed source ↗
Floodlighting works for phase 1, 210 calendar days. Tendered by main contractor China Construction Eighth Engineering Division.
Land
Site326 mu · Mar 2023 Reported source ↗
Power supply
Dedicated substation110kV · Mar 2025 Reported source ↗
The master plan includes two 110kV substation buildings. Phase 1 includes one substation building (Sina, 2024-11-21). No MVA is stated. · Applies to the whole campus.
Dedicated substation交通银行股份有限公司内蒙古自治区分行 (own phase 1 110kV substation) · 160 MVA · 110kV · Sep 2025 Confirmed source ↗
Phase 1 110/10kV substation with 2 x 80MVA on-load tap-changing transformers. Two 110kV incoming bays, one to the Hesheng (和盛) 220kV substation and one to the 110kV side of the Shengle (盛乐) 220kV substation, plus 24 planned 10kV feeders. Lines are not part of this project. Hohhot ecology bureau approval 呼环政批字〔2025〕59号, issued 15 Sep 2025. The EIA report gives substation investment of 60.33 million yuan, about 2,332 sqm of land inside the data centre site, and a 4 month build.

Sources checked 2026-10-22

  1. 规划超1万机架 交通银行和林格尔新区数据中心开工 (中国IDC圈, 2024-08-08)
  2. 2800机柜 交通银行和林格尔新区数据中心一期项目封顶 (中国IDC圈, 2024-11-22)
  3. 交通银行和林格尔新区数据中心打造金融算力新枢纽 (呼和浩特日报, 2025-03-31)
  4. 交通银行和林格尔新区数据中心一期项目顺利通过建设工程消防验收备案 (内蒙古和林格尔新区管理委员会 (规划建设局), 2026-03-23)
  5. 交通银行总行数据中心一期项目在和林格尔新区立项备案 (内蒙古和林格尔新区管理委员会 (政务服务局), 2023-03-16)
  6. 交通银行和林格尔新区数据中心一期项目泛光照明工程中标结果公告 (中化商务电子招投标平台, 2025-06-17)
  7. 泰豪成功中标交行两大数据中心项目,助力“东数西算”与金融安全 (江西省科技装备业商会 (转载泰豪公司微信公众号), 2025-09-05)
  8. 交通银行和林格尔新区数据中心一期项目机房测试和认证服务项目中标候选人公示 (中化商务电子招投标平台, 2025-07-15)
  9. 交通银行和林格尔新区数据中心一期项目110KV变电站施工采购中标候选人公示 (千里马招标网, 2024-12-05)
  10. 交通银行和林格尔新区数据中心一期项目热力接入工程采购招标公告(第二次) (中化商务电子招投标平台, 2025-04-01)
  11. 呼和浩特市生态环境局关于交通银行和林格尔新区数据中心一期110kV变电站环境影响报告表的批复 (呼和浩特市生态环境局, 2025-09-19)

More in Horinger and Hohhot

Also run by Bank of Communications

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.