Huawei Cloud North China (Horinger) Data Center
Horinger, Inner Mongolia, China · Horinger and Hohhot market · location approximate to district level
Also listed as 华为云华北(和林格尔)数据中心, 华为云和林格尔数据中心 and Huawei Cloud Horinger.
Huawei Cloud North China (Horinger) Data Center is a data center project in Horinger, China, operated by Huawei Cloud (华为云). It is operational. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: moved to operational on 12 July 2025. Record last checked against its sources on 22 October 2026.
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Huawei Cloud (华为云)
Hyperscaler self-build
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
China, 2026-10-12. China coverage is a pilot of one cluster, Zhongwei in Ningxia, entered on 12 October 2026 from Chinese-language primary and state press sources. Other Chinese hubs are not yet covered, so no China total here describes the country. Many Chinese projects publish rack counts and no megawatts. ArusGrid records the rack count and leaves capacity blank rather than convert it.
Where it sits
Horinger and Hohhot holds 10 active projects with 298 MW of planned IT load between them, and Huawei Cloud North China (Horinger) Data Center has no published figure so it sits outside that ranking. Of those, 3 are operational, 1 is operational and expanding, 1 is under construction, 2 are at the land and permitting stage and 3 are announced only. No third party publishes a colocation vacancy rate for Horinger and Hohhot, and ArusGrid does not estimate one.
Huawei has 3 others in China tracked by ArusGrid, including Huawei Cloud Gui'an Data Center, Huawei Cloud Ulanqab Data Center and Huawei Cloud East China (Wuhu) Data Centre (华为云华东(芜湖)数据中心). No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The dated record runs from under construction on 18 October 2023 to operational on 12 July 2025. The money on record is CN¥75bn as of August 2026, the announced investment. Power comes from 华为云计算技术有限公司 (own Yungu West zone phase 1 220kV substation) through a dedicated substation at 220 kV. Cooling uses hybrid air and liquid cooling.
The US export control position for advanced AI chips in China, as of 7 October 2026, is recorded as “Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026”. ArusGrid holds 10 public sources for this project, the latest dated 9 October 2026, and last checked the record on 22 October 2026.
How well evidenced is it
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes
AI workloads
StatusConfirmed
It opened in July 2025 as Huawei Cloud's first northern supernode AI computing centre (Ifeng, 2025-07-12).
Access to AI chips
GradeLicence required for a party
A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.
US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo
Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 · Licence required, presumption of denial, case-by-case review for H200-class chips since 15 January 2026 (2026-10-07) source
Stage history
Who is behind it
OperatorHuawei Cloud (华为云) · Hyperscaler self-build
Who uses the compute
Built for Huawei Cloud (华为云)'s own use. No customer workload has been tied to this building on the public record.
Money at this site
Announced investment, 2026-08CN¥75bn
The figure covers the whole campus.
Colocation price per kW of IT load per month
An own-use build. No colocation price applies.
Land
Site3,975,353 sqm · Oct 2023 Reported source ↗ Source gives 5,963 mu (398 ha) in the Horinger New Area Cloud Valley zone. Converted at 1 mu = 666.67 sqm. The planned scope covers data centres, substations, labs, R&D and production buildings, and support facilities.
Power supply
Dedicated substation220kV · Mar 2026 Reported source ↗ Yungu South zone phase 1 filing change includes three machine room buildings, a power control building and a 220kV substation; investment 930 million yuan, construction August 2023 to September 2027 · Applies to the whole campus.
Dedicated substation华为云计算技术有限公司 (own Yungu West zone phase 1 220kV substation) · 300 MVA · 220kV · Jan 2025 Confirmed source ↗ New 220kV substation with 3 x 100MVA main transformers and two 220kV incoming bays for the Yungu West zone phase 1. EIA approved under 内环表〔2025〕30号 on 24 Jan 2025. · Applies to the whole campus.
Dedicated substation华为云计算技术有限公司 (own Yungu South zone phase 1 220kV substation) · 300 MVA · 220kV · Jan 2025 Confirmed source ↗ New 220kV substation with 3 x 100MVA main transformers and two 220kV incoming bays for the Yungu South zone phase 1. EIA approved under 内环表〔2025〕35号 on 24 Jan 2025. · Applies to the whole campus.
Water and cooling
CoolingHybrid air and liquid cooling Reported source ↗ Air cooling plus liquid cooling with AI tuning. Average temperature 7C allows nearly 300 days a year of full natural cooling.
Sources checked 2026-10-22
- Hohhot city strives to be China's Cloud Valley (China Daily, 2023-10-18)
- 华为云北方首批超节点AI智算中心开服 (Ifeng Tech, 2025-07-12)
- 为何全球算力看中国 中国绿算看内蒙古 (Xinhua Finance, 2026-08-12)
- 华为云和林格尔数据中心项目-云谷西区(一期)第二批次建设工程完成竣工验收备案 (内蒙古和林格尔新区管理委员会, 2026-09-23)
- Huawei cloud data center starts up in Hohhot (China Daily, 2023-10-11)
- 总投资约66亿!内蒙古6个算力项目(变更)备案获批,涉及阿里、华为云、中国联通等 (新浪财经, 2026-03-24)
- 华为北方首个3D数据中心在和林格尔新区封顶 (中国(内蒙古)自由贸易试验区呼和浩特片区、内蒙古和林格尔新区管理委员会, 2026-10-09)
- 内蒙古自治区生态环境厅关于华为云和林格尔数据中心项目-云谷西区(一期)220kV变电站建设项目环境影响评价文件(辐射类)审批结果公示 (内蒙古自治区生态环境厅, 2025-02-10)
- 内蒙古自治区生态环境厅关于华为云和林格尔数据中心项目-云谷南区(一期)220kV变电站建设项目环境影响评价文件(辐射类)审批结果公示 (内蒙古自治区生态环境厅, 2025-02-10)
- 内蒙古自治区生态环境厅关于华为云和林格尔数据中心项目-云谷北区(一期)220kV变电站建设项目环境影响评价文件(辐射类)审批结果公示 (内蒙古自治区生态环境厅, 2025-02-10)