Digital Hyperspace Indonesia JKT1A, GIIC Cikarang is a data center project in Cikarang, Bekasi (GIIC Zone EE), Indonesia, operated by PT Digital Hyperspace Indonesia (Quantum DC). It is being commissioned. It is planned for 20 MW of IT load.
Record last checked against its sources on 20 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.
Greater Jakarta holds 37 active projects with 3,240 MW of planned IT load between them, and Digital Hyperspace Indonesia JKT1A, GIIC Cikarang ranks 27th by planned capacity. Of those, 12 are operational, 10 are operational and expanding, 8 are under construction, 1 is being commissioned, 1 is at the land and permitting stage, 3 are announced only and 2 are on hold. Published colocation vacancy in Greater Jakarta was 24.9% as of December 2025, on 322 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.
Digital Hyperspace Malaysia (Quantum DC, HK) has 1 project elsewhere in the dataset tracked by ArusGrid, including Digital Hyperspace Johor. It sits on the DHI Cikarang campus. Named funding comes from Quantum DC (HK) and Global Telecom Capital (GTC) Fund on the equity side. The named user of the compute is China Telecom (reported, unconfirmed).
Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 24 March 2025, and last checked the record on 20 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
No public signal either way.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
No figure has been announced. This range is 20 MW of planned IT load times a published benchmark of US$11.21 per watt for Jakarta, plus or minus 15 percent. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.
Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.
No published price band exists for Indonesia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Greater Jakarta · All projects in Indonesia · All Digital Hyperspace Malaysia (Quantum DC, HK) projects · All projects being commissioned · Data center rules in Indonesia · Full directory