Directory › Indonesia › Greater Jakarta › SpaceDC JAK1 (ID01 campus), West Jakarta

SpaceDC JAK1 (ID01 campus), West Jakarta

West Jakarta (Kalideres), DKI Jakarta, Indonesia · Greater Jakarta market · location approximate to district level
Why it is on hold. A partner walked awayNo progress on record The 24MW build was never reported started. The sister building was sold in 2022, the site now sits beside Digital Realty Bersama's West Jakarta campus, and the operator has said nothing about Indonesia since 2022. source The graveyard.

SpaceDC JAK1 (ID01 campus), West Jakarta is a data center project in West Jakarta (Kalideres), Indonesia, operated by SpaceDC. It is on hold. It is planned for 24 MW of IT load.

Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
On hold
Planned IT load
24 MW
Running now
Not disclosed
Operators rarely publish this
Operator
SpaceDC
Colocation
AI workloads
Unlikely
Evidence grade
Thin
Will it get built?Stalled2 of 7 gates passed
○ Land secured✓ Power arranged○ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Land secured.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.

Where it sits

Greater Jakarta holds 37 active projects with 3,240 MW of planned IT load between them, and SpaceDC JAK1 (ID01 campus), West Jakarta ranks 25th by planned capacity. Of those, 12 are operational, 10 are operational and expanding, 8 are under construction, 1 is being commissioned, 1 is at the land and permitting stage, 3 are announced only and 2 are on hold. Published colocation vacancy in Greater Jakarta was 24.9% as of December 2025, on 322 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

It is the only SpaceDC project ArusGrid tracks. It sits on the SpaceDC ID01 campus. Named funding comes from GIC on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

Power comes from on-site natural gas generators through captive generation (reported, unconfirmed).

Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 5 public sources for this project, the latest dated 18 March 2025, and last checked the record on 19 October 2026.

How well evidenced is it

The announcement stands alone, or the project is on hold. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusUnlikely

Published design density is 6 to 8kW/rack average (water-cooled racks up to 50kW offered); 2020 to 2021 design era.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Who is behind it

OperatorSpaceDC · Colocation
Funder, EquityGIC

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$229m to US$309m

No figure has been announced. This range is 24 MW of planned IT load times a published benchmark of US$11.21 per watt for Jakarta, plus or minus 15 percent. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Colocation price per kW of IT load per month

No published price band exists for Indonesia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Power supply
Own generationon-site natural gas generators · Sep 2019 Reported source ↗
2019 design, on-site gas generation with UPS and diesel backup; waste heat to absorption cooling · Applies to the whole campus.

Sources checked 2026-10-19

  1. spacedc.com
  2. datacenterdynamics.com
  3. Digital Realty Enters Indonesia Through Formation of New Joint Venture (Digital Realty via PR Newswire, 2025-03-18)
  4. BDDC hadirkan pusat data dalam kota berkapasitas 60 MW (ANTARA, 2023-05-09)
  5. Polymer Connected rebrands as SpaceDC, gives details of Jakarta campus plans (DCD, 2019-09-18)

More in Greater Jakarta

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.