The Hive (Beeinfotech PH) is a data center project in Quezon City (Bridgetowne), Philippines, operated by Bee Information Technology PH (Beeinfotech). It is operational. It is planned for 20 MW of IT load.
Latest change on record: entered the record as operational on 14 February 2022. Record last checked against its sources on 21 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Philippines approves, powers and taxes data centers is on Data center rules in Philippines.
Greater Manila holds 9 active projects with 517 MW of planned IT load between them, and The Hive (Beeinfotech PH) ranks 7th by planned capacity. Of those, 6 are operational, 1 is at the land and permitting stage, 1 is announced only and 1 is on hold. Published colocation vacancy in Greater Manila was 43.6% as of June 2026, on 90 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.
It is the only Beeinfotech project ArusGrid tracks. It sits on the The Hive campus. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The stage was recorded as operational on 14 February 2022. Power comes from National grid (utility not named) through grid supply (reported, unconfirmed).
Grid power for a large industrial user in the Philippines costs about US$0.12 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in the Philippines, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 8 public sources for this project, the latest dated 21 March 2025, and last checked the record on 21 October 2026.
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Operator states the facility is 'powered by 20MW+ for AI and traditional colocation' and it is provisioned to host AWS Outposts (an on-prem AWS hardware product, NOT an AWS tenancy). Stated AI purpose = 'likely' under the 4-tier rule. No cooling or rack-density spec published.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.
No published price band exists for Philippines, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Greater Manila · All projects in Philippines · All projects operational · Data center rules in Philippines · Full directory