STT Fairview (STT GDC 'Polaris' campus)

Quezon City, Metro Manila, Philippines · Greater Manila market · location approximate to district level

STT Fairview (STT GDC 'Polaris' campus) is a data center project in Quezon City, Philippines, operated by STT GDC Philippines. It is operational. It is planned for 124 MW of IT load. The operator reports 32 MW running.

Latest change on record: moved to operational on 4 August 2026. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
124 MW
Running now
32 MW
Operators rarely publish this
Operator
STT GDC Philippines
Joint venture
AI workloads
Likely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Philippines approves, powers and taxes data centers is on Data center rules in Philippines.

Where it sits

Greater Manila holds 9 active projects with 517 MW of planned IT load between them, and STT Fairview (STT GDC 'Polaris' campus) ranks first by planned capacity. Of those, 6 are operational, 1 is at the land and permitting stage, 1 is announced only and 1 is on hold. Published colocation vacancy in Greater Manila was 43.6% as of June 2026, on 90 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

STT GDC has 24 projects elsewhere in the dataset tracked by ArusGrid, including STT Jakarta 7 to 9 (future phases), STT Johor Campus and STT GDC Bengaluru Devanahalli campus. It sits on the STT Fairview campus. Named funding comes from KKR and Singtel on the equity side and Globe Telecom and Ayala Corporation. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The build is phased. Fairview 1 (built out) at 32 MW is operational with a 2026 target; Fairview 2 at 32 MW is announced with a 2027 target. The dated record runs from under construction on 18 May 2023 to operational on 4 August 2026. The money on record is US$1bn as of May 2025, the announced investment. Power comes from Meralco through a dedicated substation at 115 kV (reported, unconfirmed). Cooling uses air cooling.

Grid power for a large industrial user in the Philippines costs about US$0.12 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in the Philippines, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 19 public sources for this project, the latest dated 1 September 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

124MW greenfield campus; STT GDC states the buildings are engineered to house liquid-cooled solutions on customer request (DCD, May 2023); marketed as the country's largest AI-ready campus; hyperscaler anchor tenant reported (Inquirer, May 2025). No dated source for actual liquid cooling installed or GPUs deployed, so 'likely' not 'confirmed'.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Fairview 1 (built out) · Operational32 MW, target 2026
Fairview 2 · Announced32 MW, target 2027

Stage history

2023-05-18Under construction · datacenterdynamics.com
2026-08-04Operational · insiderph.com

Who is behind it

OperatorSTT GDC Philippines · Joint venture
Funder, Joint venture partnerGlobe Telecom
Funder, Joint venture partnerAyala Corporation
Funder, EquityKKR
Funder, EquitySingtel

Who uses the compute

Tenant · hyperscalerUndisclosed global cloud service provider (anchor tenant) · reported, unconfirmed

First anchor tenant at STT Fairview; MW not stated · as of 2025-05-14

Philippine Daily Inquirer quotes STT GDC Philippines CEO Carlo Malana that a global cloud service provider signed as first anchor tenant, name withheld for confidentiality. No PSE disclosure by Globe found. Adds the dated source to the existing reported client.

Source · Globe data center bags hyperscaler deal for Fairview facility (Philippine Daily Inquirer, 2025-05-14)

Money at this site

Announced investment, 2025-05US$1bn

The figure covers the whole campus.

Platform deals that include it

KKR + Singtel acquisition of STT GDC (platform M&A)
Platform acquisition, 2026-09-01
US$5.1bn
STT GDC Philippines x MPower 40.5MW clean power supply
Power deal
Not disclosed

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

No published price band exists for Philippines, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Main contractorFirst Balfour-Leighton Asia JV · Nov 2023 Confirmed source ↗
Phase 1 general contractor (civil, structural, architectural, MEPF)
Grid and substation worksMeralco Energy, Inc. (MSERV) · May 2024 Reported source ↗
Supply and installation of high-voltage gas-insulated switchgear, high-voltage oil-immersed transformers and medium-voltage dry-type transformers.
Grid and substation worksMiescor (Meralco Industrial Engineering Services Corporation) · PHP 220m · Feb 2025 · completed Reported source ↗
Joint construction of the 115kV in-building dual-feed switching station for STT Fairview (Polaris), with Harmonic System Inc.
Grid and substation worksHarmonic System Inc. · Feb 2025 · completed Reported source ↗
Joint construction of the 115kV switching station with Miescor.
Power supply
Dedicated substationMeralco · 115kV · Feb 2025 Reported source ↗
Dual-feed Polaris switching station, PHP220m, built with MIESCOR
Renewable power dealMPower (Meralco) · 40.5 MW · Apr 2026 Reported source ↗
10-year renewable supply shared with STT Cavite 2 · Applies to the whole campus.
Water and cooling
CoolingAir cooled · design PUE <1.4 Confirmed source ↗
N+4 high efficiency adiabatic air-cooled chillers in a ring configuration, with liquid cooling readiness. Factsheet covers the Fairview 1 building of 28MW IT.

Sources checked 2026-10-21

  1. datacenterdynamics.com
  2. business.inquirer.net
  3. bworldonline.com
  4. philstar.com
  5. datacenterdynamics.com
  6. meralcomain.s3.ap-southeast-1.amazonaws.com
  7. bworldonline.com
  8. pcij.org
  9. bworldonline.com
  10. bworldonline.com
  11. STT GDC explores more PHL sites for expansion (BusinessWorld, 2026-04-27)
  12. STT GDC scaling PH data center capacity to 128 MW (InsiderPH, 2026-08-04)
  13. KKR-Singtel Consortium Completes Acquisition of STTGDC; Company Launches Refreshed Global Brand for Next Phase of Growth (STT GDC via Access Newswire, 2026-09-01)
  14. Beyond GCash: Globe pinpoints its next big multi-billion-peso growth engine (Manila Bulletin, 2026-08-10)
  15. STT GDC Philippines: Building the Digital Infrastructure for the Philippines' AI Future (Globe Telecom, 2026-08-07)
  16. Meralco completes P220M switching station on QC hyperscale facility (The Philippine Star (republished by matuwid.org), 2025-02-28)
  17. STT GDC's Largest Data Center in PH Build on Track (Globe Telecom, 2023-10-10)
  18. Meralco unit to energize PH's largest data center (Philippine News Agency, 2024-05-31)
  19. Construction commences on STT Fairview Data Center Campus project in Philippines (World Construction Network (GlobalData), 2023-08-10)

More in Greater Manila

Also run by STT GDC

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.