ArusGridProject
Directory › Saudi Arabia › Dammam / Eastern Province › Aramco Digital Dammam (GroqCloud region)

Aramco Digital Dammam (GroqCloud region) data center

Dammam, Eastern Province, Saudi Arabia · Dammam / Eastern Province market · location approximate to district level

Aramco Digital Dammam (GroqCloud region) is a data center project in Dammam, Saudi Arabia, operated by Aramco Digital. It is operational. The operator has not published a capacity figure, and ArusGrid does not estimate one.

Latest change on record: entered the record as operational on 10 February 2025. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Aramco Digital
Corporate
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Saudi Arabia approves, powers and taxes data centers is on Data center rules in Saudi Arabia.

Where it sits

Dammam / Eastern Province holds 8 active projects with 370 MW of planned IT load between them, and Aramco Digital Dammam (GroqCloud region) has no published figure so it sits outside that ranking. Of those, 4 are operational, 2 are under construction, 1 is being commissioned and 1 is at the land and permitting stage. No third party publishes a colocation vacancy rate for Dammam / Eastern Province, and ArusGrid does not estimate one.

It is the only Aramco project ArusGrid tracks. Named funding comes from Saudi Aramco on the equity side. The named user of the compute is Groq (confirmed).

The stage was recorded as operational on 10 February 2025.

The US export control position for advanced AI chips in Saudi Arabia, as of 19 November 2025, is recorded as “Case-by-case authorisation only”. ArusGrid holds 1 public source for this project, the latest dated 10 February 2025, and last checked the record on 19 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesNo
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

19,000 Groq LPU accelerators are running in production as GroqCloud's second region globally. An actual deployment, not an inference from design.

Access to AI chips

GradeCommercial signal only

A chip-vendor partnership or US hyperscaler relationship has been announced, but no government document names anyone involved. Signal, not licence. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipYes

Case-by-case authorisation only · Case-by-case authorisation only (2025-11-19) source

Stage history

2025-02-10Operational · groq.com

Who is behind it

OperatorAramco Digital · Corporate
Funder, EquitySaudi Aramco

Who uses the compute

Runs compute here · GPU cloudGroq · confirmed

GroqCloud inference cluster, operational since December 2024, US$1.5bn expansion · as of 2025-02-10

Groq's own release says its Dammam data center, built with Aramco Digital, has been operational since December 2024, brought online in eight days, and is the region's largest inference cluster; Saudi Arabia committed US$1.5bn to expand it.

Source · Saudi Arabia Announces $1.5 Billion Expansion to Fuel AI-powered Economy with AI Tech Leader Groq (Groq, 2025-02-10)

Colocation price per kW of IT load per month

No published price band exists for Saudi Arabia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-10-19

  1. Saudi Arabia Announces $1.5 Billion Expansion to Fuel AI-powered Economy with AI Tech Leader Groq (Groq, 2025-02-10)

More in Dammam / Eastern Province

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.