Ezditek RUH01 data center

Riyadh, Saudi Arabia · Riyadh market · location approximate to district level

Ezditek RUH01 is a data center project in Riyadh, Saudi Arabia, operated by Ezditek. It is under construction. It is planned for 24 MW of IT load.

Latest change on record: entered the record as under construction on 1 November 2024. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
24 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Ezditek
Colocation
AI workloads
No signal either way
Evidence grade
Corroborated
Will it get built?Leaning yes4 of 7 gates passed
✓ Land secured○ Power arranged✓ Approvals granted○ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Saudi Arabia approves, powers and taxes data centers is on Data center rules in Saudi Arabia.

Where it sits

Riyadh holds 14 active projects with 1,216 MW of planned IT load between them, and Ezditek RUH01 ranks 10th by planned capacity. Of those, 1 is operational, 1 is operational and expanding, 5 are under construction, 3 are at the land and permitting stage and 4 are announced only. No third party publishes a colocation vacancy rate for Riyadh, and ArusGrid does not estimate one.

It is the only Ezditek project ArusGrid tracks. The named user of the compute is Gcore (reported, unconfirmed).

The stage was recorded as under construction on 1 November 2024.

The US export control position for advanced AI chips in Saudi Arabia, as of 19 November 2025, is recorded as “Case-by-case authorisation only”. ArusGrid holds 2 public sources for this project, the latest dated 21 November 2024, and last checked the record on 21 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderNo
Disclosed client (reported)Yes
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesNo
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

The operator markets to hyperscalers and cloud providers but names no AI tenant, workload or cooling specification.

Access to AI chips

GradeNo public signal

Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Case-by-case authorisation only · Case-by-case authorisation only (2025-11-19) source

Stage history

2024-11-01Under construction · ezditek.com

Who is behind it

OperatorEzditek · Colocation

Who uses the compute

Runs compute here · GPU cloudGcore · reported, unconfirmed

Gcore-Ezditek JV AI factory, 'tens of thousands of GPUs' planned · as of 2024-11-19

Ezditek's own release says the JV 'AI factory will be deployed in an Ezditek data center and be home to tens of thousands of GPUs'. RUH01 at Princess Nourah University is Ezditek's only data center (ground broken the same day), so the location fits exactly one project. Held at reported because the tie to RUH01 is ours and no GPU count or go-live has been published since.

Source · Gcore and Ezditek Launch Joint Venture to Accelerate Building, Training, and Deploying AI Solutions in the Kingdom of Saudi Arabia (Ezditek, 2024-11-19)

Source · Ezditek Breaks Ground on Data Center Facility in Riyadh to Provide a Foundation for AI and Cloud Innovation in the Kingdom of Saudi Arabia (Ezditek, 2024-11-19)

Colocation price per kW of IT load per month

No published price band exists for Saudi Arabia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
LandlordPrincess Nourah Bint Abdulrahman University · 35,000 sqm · Nov 2024 Reported source ↗
Site on the PNU campus. Lease terms not disclosed; the relationship is inferred.

Sources checked 2026-10-21

  1. Ezditek Breaks Ground on Data Center Facility in Riyadh to Provide a Foundation for AI and Cloud Innovation in the Kingdom of Saudi Arabia (Ezditek, 2024-11-19)
  2. Ezditek breaks ground on 24MW data center in Riyadh, Saudi Arabia (DCD, 2024-11-21)

More in Riyadh

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.