SUPERNAP Thailand (Chonburi) is a data center project in Bo Win, Si Racha (Hemaraj Chonburi IE), Thailand, operated by SUPERNAP (Thailand). It is operational. It is planned for 60 MW of IT load.
Latest change on record: moved to operational on 13 September 2017. Record last checked against its sources on 21 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.
EEC (Eastern Seaboard) holds 21 active projects with 3,703 MW of planned IT load between them, and SUPERNAP Thailand (Chonburi) ranks 13th by planned capacity. Of those, 2 are operational, 1 is operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for EEC (Eastern Seaboard), and ArusGrid does not estimate one.
China Mobile Intl has 1 project elsewhere in the dataset tracked by ArusGrid, including China Mobile International Singapore. Named funding comes from China Mobile on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.
The dated record runs from under construction on 27 January 2016 to operational on 13 September 2017. Power comes from WHA Utilities and Power (WHAUP) through onsite solar (reported, unconfirmed).
Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 8 public sources for this project, the latest dated 21 April 2022, and last checked the record on 21 October 2026.
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
2017 design era, Tier IV enterprise/interconnection colo with target PUE 1.35-1.45; no liquid-cooling or high-density disclosure.
A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
Platform capital spans several sites. It is never added to this project's own figure.
No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in EEC (Eastern Seaboard) · All projects in Thailand · All China Mobile Intl projects · All projects operational · Data center rules in Thailand · Full directory