Bo Win, Si Racha (Hemaraj Chonburi IE), Chonburi, Thailand · EEC (Eastern Seaboard) market · location approximate to district level

SUPERNAP Thailand (Chonburi) is a data center project in Bo Win, Si Racha (Hemaraj Chonburi IE), Thailand, operated by SUPERNAP (Thailand). It is operational. It is planned for 60 MW of IT load.

Latest change on record: moved to operational on 13 September 2017. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
60 MW
Running now
Not disclosed
Operators rarely publish this
Operator
SUPERNAP (Thailand)
Colocation
AI workloads
Unlikely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.

Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

Where it sits

EEC (Eastern Seaboard) holds 21 active projects with 3,703 MW of planned IT load between them, and SUPERNAP Thailand (Chonburi) ranks 13th by planned capacity. Of those, 2 are operational, 1 is operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for EEC (Eastern Seaboard), and ArusGrid does not estimate one.

China Mobile Intl has 1 project elsewhere in the dataset tracked by ArusGrid, including China Mobile International Singapore. Named funding comes from China Mobile on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The dated record runs from under construction on 27 January 2016 to operational on 13 September 2017. Power comes from WHA Utilities and Power (WHAUP) through onsite solar (reported, unconfirmed).

Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 8 public sources for this project, the latest dated 21 April 2022, and last checked the record on 21 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsNo

AI workloads

StatusUnlikely

2017 design era, Tier IV enterprise/interconnection colo with target PUE 1.35-1.45; no liquid-cooling or high-density disclosure.

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Stage history

2016-01-27Under construction · datacenterdynamics.com
2017-09-13Operational · datacenterdynamics.com

Who is behind it

OperatorSUPERNAP (Thailand) · Colocation
Funder, EquityChina Mobile

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Platform deals that include it

China Mobile acquisition of SUPERNAP Thailand
Platform acquisition, 2025-03
Not disclosed

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Main contractorThai Obayashi Corporation · completed Confirmed source ↗
SUPERNAP Thailand data centre (pre-2021, completed 2017)
Land
Industrial estateHemaraj Chonburi Industrial Estate · 12 ha · Jan 2016 Reported source ↗
Site of nearly 12 hectares.
Power supply
Dedicated substation115kV · Sep 2017 Reported source ↗
Power arrives over diverse 115kV transmission paths into two on-site substations.
On-site solarWHA Utilities and Power (WHAUP) · Apr 2022 Reported source ↗
Solar farm of about 10,000 sqm on SUPERNAP-owned land next to the data centre. WHAUP builds it and runs operation and maintenance for 20 years. Investment about THB 30 million. MWp not stated. · PPA signed April 2022. W.Media (2023-01-03) reports the solar farm was built near the facility on a turnkey basis. · Applies to the whole campus.
Water and cooling
Cooling Reported source ↗
Target PUE of 1.35 to 1.45 at opening.

Sources checked 2026-10-21

  1. datacentermap.com
  2. supernap.co.th
  3. baxtel.com
  4. app.mergerlinks.com
  5. Construction begins on SuperNAP Thailand (DatacenterDynamics, 2016-01-27)
  6. SuperNAP International opens Chonburi, Thailand data center (DatacenterDynamics, 2017-09-13)
  7. Supernap Thailand signs PPA to build solar plant (DCD, 2022-04-21)
  8. Supernap opens new data center, a step towards Thailand 4.0 vision (DataCenterNews Asia, 2017-09-14)

More in EEC (Eastern Seaboard)

Also run by China Mobile Intl

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.