Digital Edge / B.Grimm BKK Campus (Chonburi)

Chonburi (EEC), Chonburi, Thailand · EEC (Eastern Seaboard) market · location approximate to city level

Digital Edge / B.Grimm BKK Campus (Chonburi) is a data center project in Chonburi (EEC), Thailand, operated by Digital Edge. It is under construction. It is planned for 100 MW of IT load.

Latest change on record: entered the record as under construction on 4 September 2025. Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
100 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Digital Edge
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Leaning yes5 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Tenant or own use.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.

Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

Where it sits

EEC (Eastern Seaboard) holds 21 active projects with 3,703 MW of planned IT load between them, and Digital Edge / B.Grimm BKK Campus (Chonburi) ranks 12th by planned capacity. Of those, 2 are operational, 1 is operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for EEC (Eastern Seaboard), and ArusGrid does not estimate one.

Digital Edge has 5 projects elsewhere in the dataset tracked by ArusGrid, including Digital Edge CGK Campus (CGK1 to CGK4), Cikarang, Digital Edge BOM1 campus and Digital Edge EDGE2, Jakarta. It sits on the Digital Edge BKK campus. Named funding comes from Stonepeak on the equity side, Bangkok Bank, Bank of Ayudhya, HSBC, KASIKORNBANK, Mizuho, Natixis CIB, Siam Commercial Bank, SMBC and Standard Chartered as debt and B.Grimm Power. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The build is phased. BKK1 is under construction with a Q4 2026 target; BKK2 is under construction with a 2027 target. The stage was recorded as under construction on 4 September 2025. The money on record is US$1,000m as of September 2025, the announced investment. Power comes from B.Grimm Power. Cooling uses hybrid air and liquid cooling, with a design PUE of 1.25.

Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 11 public sources for this project, the latest dated 26 August 2026, and last checked the record on 22 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Operator states the campus is built to deploy AI and cloud workloads at scale and is targeting hyperscale cloud/AI customers; 100MW greenfield, PUE target 1.25, hybrid closed-loop cooling.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

BKK1 · Under constructionSize not published, target Q4 2026
BKK2 · Under constructionSize not published, target 2027

Stage history

2025-09-04Under construction · digitaledgedc.com

Who is behind it

OperatorDigital Edge · Colocation
Funder, EquityStonepeak
Funder, Joint venture partnerB.Grimm Power
Funder, DebtBangkok Bank
Funder, DebtBank of Ayudhya
Funder, DebtHSBC
Funder, DebtKASIKORNBANK
Funder, DebtMizuho
Funder, DebtNatixis CIB
Funder, DebtSiam Commercial Bank
Funder, DebtSMBC
Funder, DebtStandard Chartered

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2025-09US$1,000m

The figure covers the whole campus.

Platform deals that include it

Digital Edge / B.Grimm US$880m green loan
Debt, 2026-05
US$880m

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Power supply
Power allocation or planB.Grimm Power · Sep 2025 Confirmed source ↗
Release says the campus is powered by B.Grimm's renewable energy portfolio; type and volume not stated · B.Grimm is also the JV partner. No PPA terms published.
Renewable power dealB.Grimm Power · Sep 2025 Reported source ↗
Clean energy via direct PPA from B.Grimm's renewable portfolio. · No MW given. · Applies to the whole campus.
Water and cooling
CoolingHybrid air and liquid cooling · design PUE 1.25 Confirmed source ↗
Hybrid closed-loop cooling towers to cut water use.
CoolingClosed-loop cooling Reported source ↗
PPTV reports a closed-loop cooling system, with other measures, to cut water use. The campus also targets LEED Silver.

Sources checked 2026-10-22

  1. digitaledgedc.com
  2. datacenterdynamics.com
  3. w.media
  4. digitaledgedc.com
  5. 'Digital Edge' ผู้ลงทุนดาต้าเซ็นเตอร์ รับลูกนโยบายพลังงานไทย พร้อมแบกต้นทุนพลังงานส่วนเพิ่ม ย้ำลงทุนไทยไม่ใช่เพราะค่าไฟถูก (The Standard, 2026-08-26)
  6. ชลบุรีเนื้อหอม ดาต้าเซ็นเตอร์-ร.พ. แห่ลงทุน รับเมืองใหม่ EEC (Thansettakij, 2026-07-17)
  7. Digital Edge, B.Grimm break ground on 100MW data center in Thailand (W.Media, 2025-09-08)
  8. Digital Edge and B.Grimm Power Break Ground on First EEC Data Center (Digital Edge, 2025-09-04)
  9. B.Grimm Power and Digital Edge groundbreaking (Thai) (Mitihoon, 2025-09-04)
  10. B.Grimm Power and Digital Edge jointly begin data center project (Marketing Oops, 2025-09-04)
  11. บี.กริม เพาเวอร์ - ดิจิทัล เอดจ์ คว้าสินเชื่อสีเขียว มูลค่าสูงที่สุดในไทย (PPTV HD36, 2026-05-08)

More in EEC (Eastern Seaboard)

Also run by Digital Edge

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.