ArusGridProject
Directory › Indonesia › Greater Jakarta › Digital Edge CGK Campus (CGK1 to CGK4), Cikarang

Digital Edge CGK Campus (CGK1 to CGK4), Cikarang

Cikarang, Bekasi, West Java, Indonesia · Greater Jakarta market · location approximate to district level

Digital Edge CGK Campus (CGK1 to CGK4), Cikarang is a data center project in Cikarang, Bekasi, Indonesia, operated by Digital Edge. It is under construction. It is planned for 500 MW of IT load.

Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
500 MW
Running now
0 MW
Operators rarely publish this
Operator
Digital Edge
Colocation
AI workloads
Confirmed
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Builder appointed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.

Where it sits

Greater Jakarta holds 37 active projects with 3,240 MW of planned IT load between them, and Digital Edge CGK Campus (CGK1 to CGK4), Cikarang ranks second by planned capacity. Of those, 12 are operational, 10 are operational and expanding, 8 are under construction, 1 is being commissioned, 1 is at the land and permitting stage, 3 are announced only and 2 are on hold. Published colocation vacancy in Greater Jakarta was 24.9% as of December 2025, on 322 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Digital Edge has 1 other in Indonesia and 4 projects elsewhere in the dataset tracked by ArusGrid, including Digital Edge EDGE2, Jakarta. It sits on the Digital Edge CGK campus. Named funding comes from Stonepeak on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The build is phased. CGK1 is under construction with a Q4 2026 target; CGK2 is under construction with a Q1 2027 target; CGK3 is under construction with a Q2 2027 target. The money on record is US$4.5bn as of June 2026, the announced investment. Power comes from PLN through grid supply. Cooling uses direct liquid cooling and reclaimed water, with a design PUE of 1.25.

Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 7 public sources for this project, the latest dated 2 October 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

Operator states the campus features liquid cooling to support AI workloads, targets PUE 1.25, and is 'purpose-built for AI and data-intensive workloads' (Jun 2026 PR). CGK1 'developed in line with committed customer requirements'.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

CGK1 · Under constructionSize not published, target Q4 2026
CGK2 · Under constructionSize not published, target Q1 2027
CGK3 · Under constructionSize not published, target Q2 2027
CGK4 · AnnouncedSize not published

Who is behind it

OperatorDigital Edge · Colocation
Funder, EquityStonepeak

Who uses the compute

Tenant · hyperscalerUndisclosed committed customer · reported, unconfirmed

Checked on 2026-10-01. No document names a confirmed user beyond the rows above.

Money at this site

Announced investment, 2026-06US$4.5bn

The figure covers the whole campus.

Platform deals that include it

Digital Edge and PLN 1.45 GW single-campus power agreement (CGK Campus)
Power deal, 2026-06
Not disclosed

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

No published price band exists for Indonesia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Industrial estateGreenland International Industrial Center (GIIC), Kota Deltamas Reported source ↗
Seller likely PT Puradelta Lestari (IDX DMAS), which owns the estate
Power supply
Grid supplyPLN · 1,450 MVA · Jun 2026 Confirmed source ↗
Dual feed, 2 x 725 MVA, upgraded from 2 x 650 MVA; target PUE 1.25 · Applies to the whole campus.
Water and cooling
WaterRecycled wastewater Confirmed source ↗
CoolingDirect liquid cooling · design PUE 1.25 Confirmed source ↗
Recycled water systems and liquid cooling for AI workloads
WaterRecycled wastewater Reported source ↗
CoolingDirect liquid cooling · design PUE 1.25 Reported source ↗
Direct-to-chip liquid cooling with water recycling systems
CoolingDirect liquid cooling · design PUE 1.25 Confirmed source ↗
Liquid cooling for AI workloads.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedPT Total Bangun Persada Tbk · Main contractor · Sep 2025 source ↗
This project is one of 3 that fit. The others are PDG JC3, GIIC Kota Deltamas, PDG JC4, GIIC Bekasi.
UnconfirmedPT PLN (Persero) UIP Jawa Bagian Tengah · Grid supply · 60 MVA · May 2025 source ↗
This project is one of 3 that fit. The others are PDG JC3, GIIC Kota Deltamas, PDG JC4, GIIC Bekasi.

Sources checked 2026-10-21

  1. id.digitaledgedc.com
  2. id.digitaledgedc.com
  3. datacenterknowledge.com
  4. RI Makin Diminati, Ini 8 Rencana Pembangunan Data Center Baru pada 2026 (Bisnis.com, 2026-10-02)
  5. Digital Edge tops out first data center at new campus outside Jakarta, Indonesia (DatacenterDynamics, 2026-05-29)
  6. PLN UIP JBT Raih SLO Bay Trafo 60 MVA di Deltamas, Perkuat Infrastruktur Listrik untuk Data Center Internasional (Warta Ekonomi, 2025-05-30)
  7. Digital Edge kantongi pembiayaan hijau US$665 juta (IndoTelko, 2026-03-30)

More in Greater Jakarta

Also run by Digital Edge

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.