DCI H1 Campus (JK1 to JK6), Cibitung

Cibitung, Bekasi, West Java, Indonesia · Greater Jakarta market · location approximate to district level

DCI H1 Campus (JK1 to JK6), Cibitung is a data center project in Cibitung, Bekasi, Indonesia, operated by DCI Indonesia. It is operational and expanding. It is planned for 300 MW of IT load. The operator reports 75 MW running.

Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
300 MW
Running now
75 MW
Operators rarely publish this
Operator
DCI Indonesia
Colocation
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.

Where it sits

Greater Jakarta holds 37 active projects with 3,240 MW of planned IT load between them, and DCI H1 Campus (JK1 to JK6), Cibitung ranks third by planned capacity. Of those, 12 are operational, 10 are operational and expanding, 8 are under construction, 1 is being commissioned, 1 is at the land and permitting stage, 3 are announced only and 2 are on hold. Published colocation vacancy in Greater Jakarta was 24.9% as of December 2025, on 322 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

DCI Indonesia has 3 others in Indonesia tracked by ArusGrid, including DCI H2 Campus (H2-01, H2-02), Karawang, DCI E1, Downtown Jakarta and DCI Bintan Campus (Hyperscale 3 / H3). It sits on the DCI H1 Cibitung campus. Named funding comes from Salim Group and Anthoni Salim on the equity side. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The build is phased. JK1 is operational with a 2013 target; JK2 is operational; JK3 is operational. Power comes from PT Cikarang Listrindo Tbk (POWR) through grid supply (reported, unconfirmed). Cooling uses direct liquid cooling.

Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 7 public sources for this project, the latest dated 23 September 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

Tier IV campus marketed to hyperscalers; JK6 (36MW, launched Jun 2025) described by DCI as the largest single-build DC in Indonesia; DCI markets 6 global cloud providers on-campus. No published rack-density/liquid-cooling spec. Liquid cooling stated by w.media on 2025-06-04. JK6 building (36MW) at H1 Cibitung: liquid cooling for high-density workloads.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

JK1 · OperationalSize not published, target 2013
JK2 · OperationalSize not published
JK3 · OperationalSize not published
JK5 · Operational15 MW, target 2023
JK6 · Operational36 MW, target 2025
JK7 · Under constructionSize not published
JK8 · Under constructionSize not published

Who is behind it

OperatorDCI Indonesia · Colocation
Funder, EquitySalim Group
Funder, EquityAnthoni Salim

Who uses the compute

Tenant · hyperscalerUndisclosed global cloud providers (6) · reported, unconfirmed

Money at this site

ArusGrid estimate, building costabout US$2.9bn to US$4.3bn

No figure has been announced. This range is 300 MW of planned IT load times a published benchmark of US$11.21 per watt for Jakarta, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Colocation price per kW of IT load per month

No published price band exists for Indonesia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Power supply
Grid supplyPT Cikarang Listrindo Tbk (POWR) · Sep 2026 Reported source ↗
Kabar Bursa says electricity for the H1 Cibitung campus comes from Cikarang Listrindo's Jababeka combined cycle gas plant (PLTGU). No PPA term or capacity given. Cikarang Listrindo is a private utility, so the arrangement is recorded as grid supply. · Applies to the whole campus.
Water and cooling
CoolingDirect liquid cooling Reported source ↗
JK6 building (36MW) at H1 Cibitung: liquid cooling for high-density workloads

Sources checked 2026-10-21

  1. dci-indonesia.com
  2. baxtel.com
  3. baxtel.com
  4. Ketiban Berkah Era AI, Intip Jurus DCII dan POWR Menjaring Cuan di Lapangan (KabarBursa, 2026-09-23)
  5. Profile: DCI Indonesia signals major expansion, targets 2,000 MW capacity (Indonesia Business Post, 2026-04-01)
  6. PT DCI Indonesia Tbk dan entitas anaknya Laporan keuangan konsolidasian interim tanggal 30 Juni 2026 (Tidak Diaudit) (PT DCI Indonesia Tbk)
  7. DCI Indonesia Launches AI-Ready JK6 with 36 MW Capacity (DCI Indonesia, 2025-06-03)

More in Greater Jakarta

Also run by DCI Indonesia

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.