DAMAC Digital Cikarang AI Campus (JKT02) is a data center project in Cikarang, Bekasi, Indonesia, operated by DAMAC Digital (EDGNEX). It is at the land and permitting stage. It is planned for 144 MW of IT load.
Latest change on record: entered the record as land and permitting on 21 July 2025. Record last checked against its sources on 20 October 2026.
Next gate to watch: Power arranged.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.
Greater Jakarta holds 37 active projects with 3,240 MW of planned IT load between them, and DAMAC Digital Cikarang AI Campus (JKT02) ranks 7th by planned capacity. Of those, 12 are operational, 10 are operational and expanding, 8 are under construction, 1 is being commissioned, 1 is at the land and permitting stage, 3 are announced only and 2 are on hold. Published colocation vacancy in Greater Jakarta was 24.9% as of December 2025, on 322 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.
DAMAC Digital (EDGNEX) has 6 projects elsewhere in the dataset tracked by ArusGrid, including Skyline Data Center (DAMAC/EDGNEX) Chachoengsao, NextGen Data Center (DAMAC Digital) Navanakorn and DAMAC Digital RUH-1 (Riyadh Industrial City 2). It sits on the DAMAC Cikarang campus. Named funding comes from DAMAC Group on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.
The stage was recorded as at the land and permitting stage on 21 July 2025. The money on record is US$2.3bn as of January 2025, the announced investment.
Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 8 public sources for this project, the latest dated 26 March 2026, and last checked the record on 20 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Announced as an AI-focused data center with high-density AI racks, targeting PUE 1.32; one of the largest AI-focused DCs in SEA per operator PR.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
The figure covers the whole campus.
No published price band exists for Indonesia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.