ArusGridProject
Directory › Thailand › EEC (Eastern Seaboard) › CloudHQ BKK Campus

CloudHQ BKK Campus

Bo Win, Si Racha, Chonburi, Thailand · EEC (Eastern Seaboard) market · location approximate to district level

CloudHQ BKK Campus is a data center project in Bo Win, Si Racha, Thailand, operated by CloudHQ. It has been announced and has not yet reached the land or permitting stage. It is planned for 108 MW of IT load.

Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Announced
Planned IT load
108 MW
Running now
Not disclosed
Operators rarely publish this
Operator
CloudHQ
Colocation
AI workloads
Likely
Evidence grade
Sourced
Will it get built?Open question2 of 7 gates passed
○ Land secured✓ Power arranged○ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Land secured.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.

Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

Where it sits

EEC (Eastern Seaboard) holds 21 active projects with 3,703 MW of planned IT load between them, and CloudHQ BKK Campus ranks 11th by planned capacity. Of those, 2 are operational, 1 is operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for EEC (Eastern Seaboard), and ArusGrid does not estimate one.

It is the only CloudHQ project ArusGrid tracks. It sits on the CloudHQ BKK campus. Named funding comes from CloudHQ on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 3 public sources for this project, the latest dated 3 August 2026, and last checked the record on 22 October 2026.

How well evidenced is it

One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

>=100MW modern greenfield; CloudHQ builds exclusively for hyperscale/AI tenants and the site is sited beside other hyperscale campuses with on-site substation.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Who is behind it

OperatorCloudHQ · Colocation
Funder, EquityCloudHQ

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Colocation price per kW of IT load per month

No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Power supply
Dedicated substationOct 2026 Confirmed source ↗
CloudHQ says the 108 MW critical IT campus will have its own on-site substation. Utility not named. Status shown as planned, RFS within 22 months. The campus page is undated; date is the access date. · Applies to the whole campus.

Sources checked 2026-10-22

  1. cloudhq.com
  2. datacenters.com
  3. ‘อมตะ’ ดึง ‘CloudHQ’ ลงทุนดาต้าเซ็นเตอร์แห่งใหม่ในระยอง (Naewna, 2026-08-03)

More in EEC (Eastern Seaboard)

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.