TCS HyperVault Anakapalli is a data center project in Anakapalli district, India, operated by HyperVault (TCS). It is at the land and permitting stage. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: entered the record as land and permitting on 21 July 2026. Record last checked against its sources on 19 October 2026.
Next gate to watch: Power arranged.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How India approves, powers and taxes data centers is on Data center rules in India.
Visakhapatnam holds 9 active projects with 2,148 MW of planned IT load between them, and TCS HyperVault Anakapalli has no published figure so it sits outside that ranking. Of those, 2 are under construction, 3 are at the land and permitting stage and 4 are announced only. No third party publishes a colocation vacancy rate for Visakhapatnam, and ArusGrid does not estimate one.
HyperVault has 1 other in India tracked by ArusGrid, including TCS HyperVault Hyderabad AI campus. Named funding comes from Tata Consultancy Services and TPG on the equity side. The named user of the compute is OpenAI (reported, unconfirmed).
The stage was recorded as at the land and permitting stage on 21 July 2026.
The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 2 public sources for this project, the latest dated 21 July 2026, and last checked the record on 19 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reported OpenAI anchor tenancy, not confirmed by TCS or OpenAI at this site.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
as of 2026-07-21
Press reports say OpenAI will be HyperVault's first customer beginning with 100 MW scalable to 1 GW, site link to Anakapalli is reported not filed
Source · TCS adds Anakapalli and Pune sites to fuel its data center push (W.Media, 2026-07-21)
ArusGrid estimate, grade C. Published band for this country. Priced on the wholesale band. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.