Sify Vizag AI data centre and open CLS

Visakhapatnam, Andhra Pradesh, India · Visakhapatnam market · location approximate to district level

Sify Vizag AI data centre and open CLS is a data center project in Visakhapatnam, India, operated by Sify Infinit Spaces. It is under construction. It is planned for 50 MW of IT load.

Latest change on record: entered the record as under construction on 14 October 2025. Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
50 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Sify Infinit Spaces
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Leaning yes4 of 7 gates passed
✓ Land secured○ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

Where it sits

Visakhapatnam holds 9 active projects with 2,148 MW of planned IT load between them, and Sify Vizag AI data centre and open CLS ranks 5th by planned capacity. Of those, 2 are under construction, 3 are at the land and permitting stage and 4 are announced only. No third party publishes a colocation vacancy rate for Visakhapatnam, and ArusGrid does not estimate one.

Sify has 4 others in India tracked by ArusGrid, including Sify Rabale campus, Sify Chennai 02 Siruseri campus and Sify Noida 02. It sits on the Sify Vizag campus. Named funding comes from Sify Technologies on the equity side. No user of the capacity is on the public record as of 2026-10-02, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The stage was recorded as under construction on 14 October 2025. The money on record is US$169m as of October 2025, the announced investment.

The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 29 June 2026, and last checked the record on 22 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Stated AI purpose (Vizag's 'first AI-powered data centre') at groundbreaking; no dated deployment.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Two phases · Under construction50 MW

Stage history

2025-10-14Under construction · datacenterdynamics.com

Who is behind it

OperatorSify Infinit Spaces · Colocation
Funder, EquitySify Technologies

Who uses the compute

Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2025-10US$169m

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)INR 6,800 to INR 8,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Land
Allocated byAPIIC · 3.6 acres · Oct 2025 Reported source ↗
Rushikonda-Madhurawada IT park

Sources checked 2026-10-22

  1. India's Sify breaks ground on 50MW data center and cable landing station in Vizag (DCD, 2025-10-14)
  2. Sify's `15,266 crore Vizag data centre gets land boost (Bizz Buzz, 2026-06-29)
  3. AP Approves Sify's Rs 15,266 Crore Data Centre Expansion, Clears 3 Other Tech Projects (Deccan Chronicle, 2026-06-29)
  4. Sify Infinit Spaces Files DRHP for Rs 3,700 Crore IPO (Angel One, 2025-10-18)

More in Visakhapatnam

Also run by Sify

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.