Sify Rabale campus

Navi Mumbai, Maharashtra, India · Mumbai metro market · location approximate to district level

Sify Rabale campus is a data center project in Navi Mumbai, India, operated by Sify Infinit Spaces. It is operational and expanding. It is planned for 136 MW of IT load. The operator reports 84 MW running.

Latest change on record: entered the record as expanding on 27 September 2026. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
136 MW
Running now
84 MW
Operators rarely publish this
Operator
Sify Infinit Spaces
Colocation
AI workloads
Likely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

Where it sits

Mumbai metro holds 32 active projects with 2,694 MW of planned IT load between them, and Sify Rabale campus ranks 7th by planned capacity. Of those, 4 are operational, 5 are operational and expanding, 11 are under construction, 6 are at the land and permitting stage and 6 are announced only. Published colocation vacancy in Mumbai metro was 6.6% as of June 2025. Vacancy excludes hyperscaler self-build.

Sify has 4 others in India tracked by ArusGrid, including Sify Chennai 02 Siruseri campus, Sify Vizag AI data centre and open CLS and Sify Noida 02. It sits on the Sify Rabale campus. Named funding comes from Sify Technologies on the equity side and IFC as debt. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The build is phased. Towers 1 and 2 at 22 MW is operational; Tower 3 at 24 MW is operational; Tower 4 at 8.1 MW is operational. The stage was recorded as operational and expanding on 27 September 2026. Power comes from on-site substations through a dedicated substation at 220 kV. Cooling uses hybrid air and liquid cooling.

The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 8 public sources for this project, the latest dated 27 September 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Tower 5 marketed as hyperscale-ready at 43.2MW; Sify has publicised GPU cloud offerings.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Towers 1 and 2 · Operational22 MW
Tower 3 · Operational24 MW
Tower 4 · Operational8.1 MW
Tower 5 (30.24MW installed at Jun 2025) · Operational43 MW
Towers 11 and 12 · Under construction39 MW, target 2028
Towers 6 and 7 (MIDC and MoEFCC approvals pending) · Land and permittingSize not published
Towers 8, 9, 10 · AnnouncedSize not published

Stage history

2026-09-27Expanding · sifytechnologies.com

Who is behind it

OperatorSify Infinit Spaces · Colocation
Funder, EquitySify Technologies
Funder, DebtIFC

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$767m to US$1.1bn

No figure has been announced. This range is 136 MW of planned IT load times a published benchmark of US$6.64 per watt for Mumbai, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)INR 6,800 to INR 8,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Project team
Design and build contractorGargantuan Industrial Space Solutions Private Limited · Mar 2025 Confirmed source ↗
Built-to-suit sub-lessor: deliver two multi-storey data centre buildings (Towers 11 and 12, Plot R-978 TTC Rabale) in two phases, obtain pre-construction approvals; hand over first DC within 18 months and second within 34 months from Feb 16, 2024
Land
LandlordGargantuan Industrial Space Solutions Private Limited · 13,152.28 sqm · leased · Mar 2025 Confirmed source ↗
Plot R-978, TTC Industrial Area, Rabale, sub-leased to Sify Infinit Spaces for Towers 11 and 12 under a sub-lease agreement dated 18 Mar 2025 (term sheet 22 Sep 2023), per the DRHP. The sub-lessor holds the environmental clearance for 40,640 sqm built-up area.
Power supply
Dedicated substationon-site substations · 220kV Confirmed source ↗
Operator claims up to 70% renewable energy and 99MW of green power from solar and wind. · 110kV substation for towers 1 to 3 and 220kV GIS substation for towers 4 to 6, per operator. · Applies to the whole campus.
Dedicated substationOn-site substation · 110kV Reported source ↗
Serves Towers I to III. Towers IV to X use the 220kV GIS substation. · Applies to the whole campus.
Renewable power dealSify (PPAs, counterparties not named) · 99 MW Reported source ↗
99MW of solar and wind. Brochure says up to 79% renewable energy and 200MW+ contracted green power across Sify. · Undated operator brochure. · Applies to the whole campus.
Water and cooling
CoolingHybrid air and liquid cooling Confirmed source ↗
Tower 5 (43.2 MW built) supports up to 130 kW/rack direct-to-chip; first NVIDIA DGX-ready certified facility in India for air and liquid cooling. Sify factsheet (undated) describes air-cooled chillers with adiabatic accessories.
CoolingAir cooled Confirmed source ↗
IFC says all Sify data centres except Noida 1 use air cooling, and the company does not depend on groundwater. Rabale T5 is IGBC Platinum rated. Sify's company-wide WUE was 1.805 in FY2025, not a Rabale figure. Sify's factsheet describes air-cooled chillers with adiabatic accessories for Towers 5 to 10.

Sources checked 2026-10-21

  1. Data Centers in Mumbai, Rabale, Airoli and Vashi (Sify Technologies (operator site, accessed), 2026-09-27)
  2. IFC Project 51725 Sify Data Center (IFC, 2026-06-22)
  3. IFC partners with Sify to support expansion of data centers and strengthen digital economy through sustainability linked loan (IFC, 2026-06-18)
  4. Sify Infinit Spaces Limited Draft Red Herring Prospectus (Sify Infinit Spaces Limited via NSE, 2025-10-16)
  5. Sify Infinit Spaces Puts Around ₹3,700 Crore IPO On Hold (Kotak Neo, 2026-09-22)
  6. Rabale T5-T10 Factsheet (Sify Technologies)
  7. Rabale (Mumbai 03) Hyperscale Campus brochure (Sify Technologies)
  8. Sify Data Center (Environmental and Social Review Summary, project 51725) (International Finance Corporation, 2026-06-22)

More in Mumbai metro

Also run by Sify

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.