ArusGridProject
Directory › Singapore › Singapore › NTT SG1

NTT SG1 data center

Singapore, Singapore · Singapore market

NTT SG1 is a data center project in Singapore, operated by NTT Global Data Centers. It is operational. It is planned for 8.6 MW of IT load. The operator reports 8.6 MW running.

Latest change on record: entered the record as operational on 7 July 2025. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
8.6 MW
Running now
8.6 MW
Operators rarely publish this
Operator
NTT Global Data Centers
Colocation
AI workloads
Unlikely
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Singapore approves, powers and taxes data centers is on Data center rules in Singapore.

Where it sits

Singapore holds 39 active projects with 874 MW of planned IT load between them, and NTT SG1 ranks 19th by planned capacity. Of those, 27 are operational, 3 are operational and expanding, 3 are under construction, 1 is past financial close and 5 are announced only. Published colocation vacancy in Singapore was 4.9% as of December 2025, on 1,043 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

It is the only NTT DATA project ArusGrid tracks. It sits on the NTT Serangoon campus. Named funding comes from NTT DC REIT on the equity side. The named user of the compute is NTT Singapore (confirmed).

The stage was recorded as operational on 7 July 2025.

Grid power for a large industrial user in Singapore costs about US$0.20 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Singapore, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 6 public sources for this project, the latest dated 1 October 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusUnlikely

Completed 2012 as an 8.6 MW interconnection and enterprise colocation site. No liquid cooling or GPU deployment disclosed in REIT filings.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Stage history

2025-07-07Operational · links.sgx.com

Who is behind it

OperatorNTT Global Data Centers · Colocation
Funder, EquityNTT DC REIT

Who uses the compute

Tenant · telcoNTT Singapore · confirmed

2.7 MW · 2.7MW contracted, 31% of SG1, 3-year master services agreement 1 Apr 2026 to 31 Mar 2029 at S$474/kW · as of 2026-03-31

NTT DC REIT's SGX media release on the SG1 renewal names NTT Singapore Pte. Ltd., an indirect wholly-owned subsidiary of the sponsor NTT Limited, as the tenant renewing 2.7MW at SG1 with a 23% positive reversion.

Source · NTT DC REIT renews master lease for SG1 at 23% increase in rent (NTT DC REIT via SGXNet, 2026-03-31)

Source · NTT DC REIT renews master lease for SG1 at 23% increase in rent (The Edge Singapore via Yahoo Finance, 2026-03-31)

Colocation price per kW of IT load per month

Observed, grade ASGD 474

issuer-stated renewal rent on a related-party contract (the sponsor, NTT Singapore, 2.7 MW, 31 percent of the asset) from 1 April 2026, up 23 percent from S$385 Electricity unstated. As of 2026-03. NTT DC REIT Manager, 2026-03-31

A contracted rent on a sponsor lease, which is a related-party figure and not market evidence on its own. The prospectus separately states an average pass-through base rent of US$277 per kW per month at December 2024 for the contracts that make up 80.9 percent of the asset's base rent, electricity excluded.

Land
LandlordJTC Corporation · leasehold · Jul 2025 Confirmed source ↗
JTC land lease expires Aug 2040 with covenant to extend a further 30 years if investment criteria and plot ratio conditions are met

Sources checked 2026-10-21

  1. NTT DC REIT Registration Prospectus (NTT DC REIT via SGX, 2025-07-07)
  2. NTT DC REIT renews SG1 Master Services Agreement with NTT Singapore (NTT DC REIT via SGX, 2026-03-31)
  3. NTT DC REIT Delivers FY25/26 DPU of 5.56 US cents (NTT DC REIT via SGX, 2026-05-12)
  4. NTT DC REIT 1Q FY26/27 Results (Minichart, 2026-09-01)
  5. NTT Serangoon Data Center (SG1) (PeeringDB, 2026-10-01)
  6. 1Q FY26/27 Business Update (NTT DC REIT (SGX filing), 2026-08-12)

More in Singapore

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.