DC1 is a data center project in Singapore, operated by Keppel DC REIT. It is operational. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: entered the record as operational on 2 February 2026. Record last checked against its sources on 13 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Singapore approves, powers and taxes data centers is on Data center rules in Singapore.
Singapore holds 39 active projects with 874 MW of planned IT load between them, and DC1 has no published figure so it sits outside that ranking. Of those, 27 are operational, 3 are operational and expanding, 3 are under construction, 1 is past financial close and 5 are announced only. Published colocation vacancy in Singapore was 4.9% as of December 2025, on 1,043 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.
Keppel has 8 others in Singapore and 1 project elsewhere in the dataset tracked by ArusGrid, including Keppel DC SGP 11, Jurong Island (DC-CFA2), Keppel Floating Data Centre and Keppel DC Singapore 1. It sits on the DC1 campus. Named funding comes from Keppel DC REIT on the equity side. The named user of the compute is 1-Net Singapore (Mediacorp subsidiary) (reported, unconfirmed).
The stage was recorded as operational on 2 February 2026.
Grid power for a large industrial user in Singapore costs about US$0.20 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Singapore, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 2 public sources for this project, the latest dated 23 July 2026, and last checked the record on 13 October 2026.
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Single tenant facility completed 2016. Tenant not named and no liquid cooling or GPU deployment disclosed.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Whole building, triple-net master lease, ~17 years remaining at Sep 2019, WALE 10.3 years at Dec 2025 · as of 2019-09-16
Keppel DC REIT's SGX acquisition announcement names the asset '1-Net North DC' on a triple-net master lease with ~17 years remaining and FY2025 results show DC1 as single-tenant at 100%; Mingtiandi's same-day report says the lessee is a subsidiary of Mediacorp (1-Net Singapore). The filing itself does not print the tenant's name, so this stays reported.
Source · Keppel DC REIT Beefs Up SG Bit Barn Portfolio with S$585M Pair of Deals (Mingtiandi, 2019-09-16)
Source · Keppel DC REIT announces two data centre acquisitions in Singapore and launches equity fund raising (Keppel DC REIT via SGXNet, 2019-09-16)
The published band for Singapore is too wide to say anything useful about this building (range wider than half its midpoint, withheld), so no estimate is shown. The band itself is on the Colo prices page.
All projects in Singapore · All projects in Singapore · All Keppel projects · All projects operational · Data center rules in Singapore · Full directory