Gulf Data Hub Dubai Silicon Oasis campus is a data center project in Dubai Silicon Oasis, United Arab Emirates, operated by Gulf Data Hub. It is operational and expanding. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: entered the record as expanding on 14 January 2025. Record last checked against its sources on 19 October 2026.
This project is built or running, so every gate counts as passed.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How United Arab Emirates approves, powers and taxes data centers is on Data center rules in United Arab Emirates.
Dubai holds 6 active projects with 129 MW of planned IT load between them, and Gulf Data Hub Dubai Silicon Oasis campus has no published figure so it sits outside that ranking. Of those, 1 is operational, 1 is operational and expanding, 1 is under construction and 3 are announced only. No third party publishes a colocation vacancy rate for Dubai, and ArusGrid does not estimate one.
Gulf Data Hub has 1 other in the United Arab Emirates tracked by ArusGrid, including Gulf Data Hub Abu Dhabi (ICAD). Named funding comes from KKR on the equity side. The named user of the compute is Etisalat (e&) (confirmed).
The stage was recorded as operational and expanding on 14 January 2025.
The US export control position for advanced AI chips in the United Arab Emirates, as of 14 July 2026, is recorded as “Country Group A:5 with Supplement No. 8 approved end users”. ArusGrid holds 2 public sources for this project, the latest dated 14 January 2025, and last checked the record on 19 October 2026.
Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.
Multi-tenant colocation. No AI tenant, workload or cooling disclosure.
Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria are published on the Methodology page.
Country Group A:5 with Supplement No. 8 approved end users · Country Group A:5 with Supplement No. 8 approved end users (2026-07-14) source
Exclusive 15-year wholesale lease of full capacity of the two DSO buildings (3,000 sqm data space each) · as of 2018-11-01
Gulf News reports Etisalat signed an exclusive 15-year wholesale lease with Gulf Data Hub for the full capacity of its Tier III data centre at Dubai Silicon Oasis
Source · Etisalat signs 15-year lease pact with Gulf Data Hub (Gulf News, 2018-11-01)
No published price band exists for United Arab Emirates, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.