CapitaLand Data Centre Navi Mumbai

Navi Mumbai, Maharashtra, India · Mumbai metro market · location approximate to district level

CapitaLand Data Centre Navi Mumbai is a data center project in Navi Mumbai, India, operated by CapitaLand India. It is operational and expanding. It is planned for 71 MW of IT load. The operator reports 34 MW running.

Latest change on record: moved to expanding on 2 January 2026. Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Expanding
Planned IT load
71 MW
Running now
34 MW
Operators rarely publish this
Operator
CapitaLand India
Colocation
AI workloads
No signal either way
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How India approves, powers and taxes data centers is on Data center rules in India.

Where it sits

Mumbai metro holds 32 active projects with 2,694 MW of planned IT load between them, and CapitaLand Data Centre Navi Mumbai ranks 14th by planned capacity. Of those, 4 are operational, 5 are operational and expanding, 11 are under construction, 6 are at the land and permitting stage and 6 are announced only. Published colocation vacancy in Mumbai metro was 6.6% as of June 2025. Vacancy excludes hyperscaler self-build.

It is the only CapitaLand project ArusGrid tracks. It sits on the CapitaLand DC Mumbai campus. Named funding comes from CapitaLand India Trust and CapitaLand India Data Centre Fund on the equity side. No user of the capacity is on the public record as of 2026-10-03, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The build is phased. Tower 1 at 34 MW is operational with a 2025 target; Tower 2 at 37 MW is under construction with a 2026 target. The dated record runs from operational on 12 August 2025 to operational and expanding on 2 January 2026. Power comes from Utility not named (in-premise 220kV GIS substation) through a dedicated substation at 220 kV.

The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 12 public sources for this project, the latest dated 15 October 2026, and last checked the record on 22 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (confirmed)Yes
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

No public signal either way.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Tower 1 · Operational34 MW, target 2025
Tower 2 · Under construction37 MW, target 2026

Stage history

2025-08-12Operational · mti.gov.sg
2026-01-02Expanding · dcnnmagazine.com

Who is behind it

OperatorCapitaLand India · Colocation
Funder, EquityCapitaLand India Trust
Funder, EquityCapitaLand India Data Centre Fund

Who uses the compute

Tenant · hyperscalerUndisclosed global hyperscaler · confirmed

Both towers · as of 2026-07-29

CLINT's 1H 2026 release says Tower 1 was fully handed over to the hyperscaler tenant in July 2026 and both towers are fully leased to a global hyperscaler, unnamed in filings.

Source · CapitaLand India Trust records 8% increase in 1H 2026 distributable income (CapitaLand, 2026-07-29)

Money at this site

ArusGrid estimate, building costabout US$401m to US$542m

No figure has been announced. This range is 71 MW of planned IT load times a published benchmark of US$6.64 per watt for Mumbai, plus or minus 15 percent. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Platform deals that include it

CapitaLand MoU with Maharashtra, US$2.2bn over five years
Other, 2025-08-12
US$2.2bn

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CINR 6,800 to INR 8,900 (about USD 81 to 106)

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity unstated in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)INR 6,800 to INR 8,900 Cushman & Wakefield for Sify Infinit Spaces, 2025-10-16
Land
Land sellerSuresh Wavia and Jayesh Vavia (sellers of the Datascape Realty SPV) · 6.6 acres · leasehold · Jul 2021 Confirmed source ↗
MIDC leasehold expiring 2062 to 2063, renewable for 95 years. Three sub-plots on Thane-Belapur Road. The filing gives a valuation, not a price.
Industrial estateMIDC (TTC Industrial Area) · 26,614 sqm · Jul 2023 Confirmed source ↗
Plot No. 14/2, 15 and 37, TTC Industrial Area, MIDC, Village Digha, Thane. Total built-up area 84,083.53 sqm.
Power supply
Dedicated substationUtility not named (in-premise 220kV GIS substation) · 220kV · Jan 2025 Confirmed source ↗
CLINT reported the GIS cabling and 220kV GIS contract awarded (contractor not named). The factsheet lists an in-premise 220kV GIS substation. · Applies to the whole campus.
On-site solarDatascape Realty (onsite) · 0.175 MW · Apr 2024 Confirmed source ↗
321 solar PV panels planned onsite to generate 175kW, 6.1% of the 2,871kW non-process load. An open-access renewable PPA is planned. Vendors are identified but none is signed in the filing. · Applies to the whole campus.
Water and cooling
Coolingdesign PUE 1.4 Confirmed source ↗
WaterMIDC Confirmed source ↗
The site uses an existing MIDC water supply connection. No groundwater is extracted in construction or operation.
CoolingAir cooled Confirmed source ↗
N+4 redundant air-cooled chillers and N+2 CRAC units per data hall. Liquid cooling is an option. 24 data halls of 2.5MW to 2.7MW IT each.

Sources checked 2026-10-22

  1. CapitaLand India Trust divests data centre stakes (DCNN, 2026-01-02)
  2. Remarks by Deputy Prime Minister and Minister for Trade and Industry Gan Kim Yong at the Opening of CapitaLand's Data Centre in Navi Mumbai (Singapore MTI, 2025-08-12)
  3. CapitaLand India Trust records 8% increase in 1H 2026 distributable income (CapitaLand, 2026-07-29)
  4. CapitaLand India Trust 1Q 2026 business update (CapitaLand India Trust, 2026-04-28)
  5. CapitaLand India Trust gains leasing momentum with second hyperscaler agreement for data centre (CapitaLand, 2026-01-15)
  6. CapitaLand Investment reaffirms long term commitment to Tamil Nadu with unveiling of new Chennai data centre (CapitaLand Investment, 2026-10-15)
  7. Proposed Investment for Development of a Data Centre Project Located in Navi Mumbai, India (Ascendas India Trust (SGX), 2021-07-05)
  8. DBS Vickers Pulse of Asia Conference 2025 (CapitaLand India Trust (SGX filing), 2025-01-08)
  9. Compliance Report 2024, Proposed Data Centre project at Plot No. 14/2, 15 & 37, TTC Industrial Area, MIDC (SIA/MH/INFRA2/401478/2022) (Datascape Realty / MoEFCC PARIVESH, 2024-04-18)
  10. CapitaLand DC Navi Mumbai 1 Factsheet (CapitaLand)
  11. Consent to Establish proposed data center, under RED category (Maharashtra Pollution Control Board, 2023-07-11)
  12. CapitaLand India Trust Raises Rs 1,300 Cr Debt To Construct Data Centres In Navi Mumbai (Outlook Business, 2023-11-11)

More in Mumbai metro

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.