SIAM.AI Cloud AI Data Center is a data center project in Bangkok (site undisclosed), Thailand, operated by SIAM.AI Cloud (Siam AI Corp). It has been announced and has not yet reached the land or permitting stage. It is planned for 100 MW of IT load.
Record last checked against its sources on 22 October 2026.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.
Bangkok metro holds 23 active projects with 893 MW of planned IT load between them, and SIAM.AI Cloud AI Data Center ranks third by planned capacity. Of those, 6 are operational, 3 are operational and expanding, 5 are under construction, 2 are being commissioned, 3 are at the land and permitting stage and 4 are announced only. Published colocation vacancy in Bangkok metro was 22.1% as of June 2026, on 113 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.
It is the only SIAM.AI project ArusGrid tracks. Named funding comes from Siam AI Corporation on the equity side. The named user of the compute is Thai government / sovereign AI users (reported, unconfirmed).
The money on record is THB 3.3bn (about US$101m) as of January 2025, the announced investment.
Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 7 public sources for this project, the latest dated 13 February 2025, and last checked the record on 22 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Thailand's only NVIDIA Cloud Partner; live NVIDIA H100 cluster with stated migration to H200 and GB200 Grace Blackwell - actual GPU deployment.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-01. No document names a confirmed user beyond the rows above.
It includes GPUs and IT hardware, so it is not comparable with building cost.
No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Bangkok metro · All projects in Thailand · All projects announced only · Data center rules in Thailand · Full directory