Evolution DC / Central Pattana Bangkok is a data center project in Bang Na, Thailand, operated by Evolution Data Centres. It is under construction. It is planned for 52 MW of IT load.

Latest change on record: entered the record as under construction in December 2024. Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
52 MW
Running now
0 MW
Operators rarely publish this
Operator
Evolution Data Centres
Joint venture
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Builder appointed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.

Thailand, 2026-09-24. Thailand asked developers on 4 September 2026 to pause 49 data centres under construction and froze 117 pending approvals while it writes new rules, due by mid October. The government has said it cannot legally enforce the pause. No list of affected projects has been published, so no Thai project has changed stage on this basis. A separate data centre electricity tariff has been created with no rate set.

Where it sits

Bangkok metro holds 23 active projects with 893 MW of planned IT load between them, and Evolution DC / Central Pattana Bangkok ranks 5th by planned capacity. Of those, 6 are operational, 3 are operational and expanding, 5 are under construction, 2 are being commissioned, 3 are at the land and permitting stage and 4 are announced only. Published colocation vacancy in Bangkok metro was 22.1% as of June 2026, on 113 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Evolution DC has 1 other in Thailand and 2 projects elsewhere in the dataset tracked by ArusGrid, including Evolution TH02 Bangkok. Named funding comes from Warburg Pincus on the equity side, International Finance Corporation as debt and Central Pattana. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The build is phased. Phase 1 at 12 MW is commissioning with a 2026 target; Phase 2 at 40 MW is under construction with a 2027 target. The stage was recorded as under construction in December 2024. Power comes from Metropolitan Electricity Authority (MEA) through grid supply. Cooling uses hybrid air and liquid cooling.

Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 9 public sources for this project, the latest dated 7 September 2026, and last checked the record on 22 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Confirmed hyperscaler anchor on phase 1 (Evolution, via DCD 2026-09-04) on a 2024-design carrier-neutral build. Tenant identity undisclosed.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Phase 1 · Commissioning12 MW, target 2026
Phase 2 · Under construction40 MW, target 2027

Stage history

2024-12Under construction · disclosures.ifc.org

Who is behind it

OperatorEvolution Data Centres · Joint venture
Funder, EquityWarburg Pincus
Funder, Joint venture partnerCentral Pattana
Funder, DebtInternational Finance Corporation

Who uses the compute

Tenant · hyperscalerUndisclosed tier-1 global hyperscaler · reported, unconfirmed

12 MW · Pre-lease of the full 12MW first phase of TH01, multi-year; phase 2 adds 40MW in Q2 2027 · as of 2026-09-04

DCD reports Evolution DC signed a multi-year pre-lease for the whole 12MW phase 1 of TH01 Bang Na with an unnamed tier 1 global hyperscaler, ready for service Q4 2026. ArusGrid carries this client as confirmed; the only document found is press, so the sourced status is reported unless Evolution's own release or the IFC disclosure is located.

Source · Evolution DC signs pre-lease for first phase of Bangkok data center to unnamed hyperscaler (DCD, 2026-09-04)

Platform deals that include it

IFC loan to Evolution DC Thailand
Debt, 2025-12-15
US$150m

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
LandlordCentral Pattana PCL · 20,470 sqm · Jun 2023 Reported source ↗
Central Pattana is JV/land partner for TH01 Bang Na; tenure not disclosed
Power supply
Grid supplyMetropolitan Electricity Authority (MEA) · Nov 2025 Confirmed source ↗
Expected use about 565,000MWh a year at full build, of which phase 1 about 158,000MWh. · Applies to the whole campus.
Power allocation or planUnnamed Thai renewable energy provider · Nov 2025 Confirmed source ↗
MoU targeting 35% of energy from renewables. Annual use about 565,000 MWh at full capacity, Phase 1 about 158,000 MWh. · Phase 1 has 12 backup diesel generators of 2MW each. Grid supply is MEA, already held.
Water and cooling
WaterMains drinking water · Metropolitan Waterworks Authority (MWA) · 1,670 m³ a day Confirmed source ↗
CoolingHybrid air and liquid cooling Confirmed source ↗
Phase 1 is air-cooled and uses no cooling water. Phase 2 is liquid-cooled and needs about 1,670 cubic metres of water a day.

Sources checked 2026-10-22

  1. datacenterdynamics.com
  2. w.media
  3. baxtel.com
  4. Markets, TH01 Bangkok phase 1 12MW sold RFS Q4 2026, phase 2 40MW RFS Q2 2027 (Evolution Data Centres, 2026-08-01)
  5. IFC project disclosure 48198, Evolution DC (Thailand) Co. Ltd. (International Finance Corporation, 2025-12-15)
  6. Evolution DC signs pre-lease for first phase of Bangkok data center to unnamed hyperscaler (DatacenterDynamics, 2026-09-04)
  7. 48198 - Evolution DC TH (Environmental and Social Review Summary) (IFC, 2025-11-14)
  8. Evolution sells data center in Thailand to hyperscaler (W.Media, 2026-09-07)
  9. Evolution DC TH (IFC-48198) (Early Warning System (Rights in Development), mirroring IFC disclosure, 2025-12-29)

More in Bangkok metro

Also run by Evolution DC

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.