Evolution DC VN HCMC (VN02) is a data center project in Thu Duc (SHTP), Vietnam, operated by Evolution Data Centres. It is at the land and permitting stage. It is planned for 52 MW of IT load.

Latest change on record: entered the record as land and permitting in April 2026. Record last checked against its sources on 20 October 2026.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
52 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Evolution Data Centres
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Open question2 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Vietnam approves, powers and taxes data centers is on Data center rules in Vietnam.

Where it sits

HCMC metro holds 10 active projects with 722 MW of planned IT load between them, and Evolution DC VN HCMC (VN02) ranks 6th by planned capacity. Of those, 2 are operational, 1 is under construction, 5 are at the land and permitting stage and 2 are announced only. Published colocation vacancy in HCMC metro was 34.8% as of June 2026, on 33 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Evolution DC has 3 projects elsewhere in the dataset tracked by ArusGrid, including Evolution TH02 Bangkok, Evolution PH01 Manila (Gateway Business Park, General Trias) and Evolution DC / Central Pattana Bangkok. It sits on the Saigon Hi-Tech Park alongside CMC Hyperscale DC SHTP, FPT Fornix HCM02, Gaw Capital Project Vespa and StarMason Data Centre Campus. Named funding comes from Evolution Data Centres, Hathor and Frontier on the equity side. No user of the capacity is on the public record as of 2026-10-02, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The stage was recorded as at the land and permitting stage in April 2026. The money on record is US$508.78m as of April 2026, a government approval ceiling.

Grid power for a large industrial user in Vietnam costs about US$0.073 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Vietnam, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:1), no named authorisation found”. ArusGrid holds 10 public sources for this project, the latest dated 24 September 2026, and last checked the record on 20 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

The IRC filing describes it as serving cloud computing, AI and big-data processing; Uptime Tier III+ targeting Tier IV; 52MW modern greenfield by an international hyperscale-focused operator (Evolution also builds a 69MW PH campus and a 52MW TH facility). No liquid-cooling spec or GPU tenant, so 'likely'.

Access to AI chips

GradeNo public signal

Nothing found in the public record. This describes the record, not the company, and it is not evidence that access was sought or denied. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

Licence required as enforced (Country Group D:1), no named authorisation found · Licence required as enforced (Country Group D:1), no named authorisation found (2026-09-27) source

Phases

VN02 full build · Land and permitting52 MW, target 2027

Stage history

2026-04Land and permitting · technode.global

Who is behind it

OperatorEvolution Data Centres · Colocation
Funder, EquityEvolution Data Centres
Funder, EquityHathor
Funder, EquityFrontier

Who uses the compute

Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Approved by a government investment agency, 2026-04US$508.78m

An approval figure is an incentive ceiling. It often covers a first phase and can exclude land or IT equipment.

Colocation price per kW of IT load per month

No published price band exists for Vietnam, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Land
Allocated byHo Chi Minh City / Saigon Hi-Tech Park · 5 ha · leasehold · Aug 2026 Reported source ↗
50-year lease
Allocated byHo Chi Minh City People's Committee (Saigon Hi-Tech Park) · 49,500 sqm · leased · Aug 2026 Reported source ↗
Lot T8 in the Hi-Tech Park, leased without auction or tender.
Power supply
Power allocation or planApr 2026 Reported source ↗
At least 30 percent renewable · The investment certificate commits the project to at least 30 percent renewable energy and net zero by 2045. Supply route not stated.

Sources checked 2026-10-20

  1. en.sggp.org.vn
  2. technode.global
  3. danviet.vn
  4. Markets, VN02 Ho Chi Minh City 52MW IT load, RFS Q4 2027 (Evolution Data Centres, 2026-08-01)
  5. Vietnam leases 5 hectares to Singapore-backed Evolution for $508M hyperscale data center (TNGlobal, 2026-08-20)
  6. Evolution DC secures long-term lease for land in Ho Chi Mihn City, Vietnam (DCD, 2026-08-21)
  7. Evolution leases 50,000 sqm land to build 52MW data center in Ho Chi Minh City (W.Media, 2026-08-27)
  8. Hơn 1,2 tỷ USD đăng ký đầu tư vào Khu Công nghệ cao TP.HCM trong 9 tháng 2026 (Báo Đầu tư, 2026-09-24)
  9. TPHCM trao chứng nhận đầu tư cho 4 dự án công nghệ cao, tổng vốn hơn 1,23 tỷ USD (Sài Gòn Giải Phóng, 2026-04-25)
  10. Evolution rents five hectares for data centre in Ho Chi Minh City (Vietnam Investment Review, 2026-08-20)

Same campus, Saigon Hi-Tech Park

More in HCMC metro

Also run by Evolution DC

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.