NTT Bangkok 4 (BKK4), Amata City Chonburi is a data center project in Amata City Chonburi Industrial Estate, Thailand, operated by NTT Global Data Centers. It is under construction. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Record last checked against its sources on 22 October 2026.
Next gate to watch: Power arranged.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Thailand approves, powers and taxes data centers is on Data center rules in Thailand.
EEC (Eastern Seaboard) holds 21 active projects with 3,703 MW of planned IT load between them, and NTT Bangkok 4 (BKK4), Amata City Chonburi has no published figure so it sits outside that ranking. Of those, 2 are operational, 1 is operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for EEC (Eastern Seaboard), and ArusGrid does not estimate one.
NTT GDC has 2 others in Thailand and 3 projects elsewhere in the dataset tracked by ArusGrid, including NTT Bangkok 2 & 3 (Amata City Chonburi) and NTT Bangkok 5 (BKK5), Chonburi. It sits on the NTT Amata City Chonburi campus alongside NTT Bangkok 2 & 3 (Amata City Chonburi) and NTT Bangkok 5 (BKK5), Chonburi. Named funding comes from NTT on the equity side. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.
Power comes from Amata B.Grimm Power (B.Grimm Power PCL).
Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 15 July 2026, and last checked the record on 22 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
Reaching this stage requires a dated construction source, which corroborates the project on its own.
100MW of contracted power for a single new building, 2026-27 vintage, from an operator whose current builds are liquid-cooling-ready. No cooling/density spec published for BKK4 specifically.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
No published price band exists for Thailand, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in EEC (Eastern Seaboard) · All projects in Thailand · All NTT GDC projects · All projects under construction · Data center rules in Thailand · Full directory