ArusGridProject
Directory › Bahrain › Manama › AWS Middle East (Bahrain) region, me-south-1

AWS Middle East (Bahrain) region, me-south-1 data center

Manama, Capital Governorate, Bahrain · Manama market · location approximate to city level
Why it is on hold. Physical damage or conflict Strikes in 2026 damaged facilities across several availability zones and took the region offline. AWS says it is replacing the infrastructure and will update its Bahrain plans in early 2027. source The graveyard.

AWS Middle East (Bahrain) region, me-south-1 is a data center project in Manama, Bahrain, operated by Amazon Web Services. It is on hold. The operator has not published a capacity figure, and ArusGrid does not estimate one.

Latest change on record: moved to on hold on 16 September 2026. Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
On hold
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Amazon Web Services
Hyperscaler self-build
AI workloads
No signal either way
Evidence grade
Thin
Will it get built?Stalled2 of 7 gates passed
○ Land secured○ Power arranged○ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Land secured.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Bahrain approves, powers and taxes data centers is on Data center rules in Bahrain.

Where it sits

Manama holds 2 active projects with 60 MW of planned IT load between them, and AWS Middle East (Bahrain) region, me-south-1 has no published figure so it sits outside that ranking. Of those, 1 is under construction and 1 is on hold. No third party publishes a colocation vacancy rate for Manama, and ArusGrid does not estimate one.

AWS has 11 projects elsewhere in the dataset tracked by ArusGrid, including AWS Thane (Balkum-Majiwada), AWS CGK Kutanegara (Karawang) and AWS CGK Margamulya (KIIC Karawang). It sits on the AWS me-south-1 campus. Named funding comes from Amazon on the equity side. The named user of the compute is Amazon Web Services (confirmed).

The dated record runs from operational on 30 July 2019 to on hold on 16 September 2026.

Grid power for a large industrial user in Bahrain costs about US$0.095 per kWh as of September 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Bahrain, as of 27 September 2026, is recorded as “Licence required as enforced (Country Group D:4), no named authorisation found”. ArusGrid holds 7 public sources for this project, the latest dated 17 September 2026, and last checked the record on 22 October 2026.

How well evidenced is it

The announcement stands alone, or the project is on hold. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusNo signal either way

No public signal either way.

Access to AI chips

GradeCommercial signal only

A chip-vendor partnership or US hyperscaler relationship has been announced, but no government document names anyone involved. Signal, not licence. Criteria are published on the Methodology page.

US licence required for this destination as enforcedYes
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectYes
Named chip-vendor partnershipNo

Licence required as enforced (Country Group D:4), no named authorisation found · Licence required as enforced (Country Group D:4), no named authorisation found (2026-09-27) source

Stage history

2019-07-30Operational · aws.amazon.com
2026-09-16On hold · datacenterdynamics.com

Who is behind it

OperatorAmazon Web Services · Hyperscaler self-build
Funder, EquityAmazon

Who uses the compute

Own use · hyperscalerAmazon Web Services · confirmed

Me-south-1 region, two Amazon-registered buildings, DC52 (Hamala) and DC53 (Askar). Region damaged across multiple AZs, AWS says it cannot restore resources · as of 2026-09-16

Amazon's own PeeringDB facility records (org Amazon.com, Inc., created 2020-03-09, updated 2025-09-26) place its Bahrain buildings in Hamala and Askar with Amazon AS16509 present. DCD quotes AWS that in me-south-1 'damage to our infrastructure spanned multiple availability zones and exceeded what our regional and multi-AZ services are designed to withstand' and it is unable to restore the region.

Source · PeeringDB facility records: AWS Bahrain DC52 MMR (Hamala) and AWS Bahrain DC53 MMR (Askar), org Amazon.com, Inc. (PeeringDB, 2025-09-26)

Source · AWS "unable to restore access" to data centers hit by Iran strikes (DCD, 2026-09-16)

Colocation price per kW of IT load per month

An own-use build. No colocation price applies.

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-10-22

  1. Now Open – AWS Middle East (Bahrain) (AWS, 2019-07-30)
  2. Amazon confirms two UAE data centers hit by drone strikes, third in Bahrain damaged (DCD, 2026-03-02)
  3. Amazon says AWS Bahrain region 'disrupted' following drone activity (Al Jazeera, 2026-03-24)
  4. Iran says it's struck offline AWS facility in Bahrain ... again (The Register, 2026-07-21)
  5. AWS "unable to restore access" to data centers hit by Iran strikes (DCD, 2026-09-16)
  6. Iranian strikes on AWS facilities left customer data beyond recovery in Bahrain, UAE (Help Net Security, 2026-09-17)
  7. Amazon AWS unable to restore access to Bahrain, one UAE cloud data zone after war (Khaleej Times (Reuters), 2026-09-16)

More in Manama

Also run by AWS

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.