DDSP Sedenak Campus is a data center project in Sedenak (Kulai), Malaysia, operated by DDSP (Digital Decarbonization Solutions Platform). It has closed its financing and construction has not been confirmed. It is planned for 45 MW of IT load.
Latest change on record: entered the record as financing closed on 3 June 2026. Record last checked against its sources on 21 October 2026.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.
Johor holds 43 active projects with 4,880 MW of planned IT load between them, and DDSP Sedenak Campus ranks 25th by planned capacity. Of those, 3 are operational, 9 are operational and expanding, 11 are under construction, 1 is past financial close, 5 are at the land and permitting stage and 14 are announced only. Published colocation vacancy in Johor was 0.7% as of June 2026, on 897 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.
It is the only DDSP project ArusGrid tracks. It sits on the Sedenak Tech Park. Named funding comes from BlackRock on the equity side. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.
The stage was recorded as past financial close on 3 June 2026. The money on record is US$283m as of May 2026, debt raised, which ArusGrid keeps out of capital totals.
Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 5 public sources for this project, the latest dated 3 June 2026, and last checked the record on 21 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
45MW liquid-cooled AI-ready build-to-suit per May 2026 financing announcements; reportedly fully pre-contracted
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
This is the size of a loan. ArusGrid excludes it from capital spending totals.
The figure covers the whole campus.
No published price band exists for Malaysia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Johor · All projects in Malaysia · All projects past financial close · Data center rules in Malaysia · Full directory