Directory › Malaysia › Johor › Racks Central Johor Campus

Racks Central Johor Campus

Pasir Gudang, Johor, Malaysia · Johor market · location approximate to district level

Also listed as Racks Central Pasir Gudang.

Racks Central Johor Campus is a data center project in Pasir Gudang, Malaysia, operated by Racks Central (Singapore). It is under construction. It is planned for 70 MW of IT load.

Latest change on record: entered the record as under construction on 11 December 2025. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
70 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Racks Central (Singapore)
Colocation
AI workloads
Confirmed
Evidence grade
Corroborated
Will it get built?Leaning yes5 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Tenant or own use.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.

Where it sits

Johor holds 43 active projects with 4,880 MW of planned IT load between them, and Racks Central Johor Campus ranks 23th by planned capacity. Of those, 3 are operational, 9 are operational and expanding, 11 are under construction, 1 is past financial close, 5 are at the land and permitting stage and 14 are announced only. Published colocation vacancy in Johor was 0.7% as of June 2026, on 897 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Racks Central has 1 project elsewhere in the dataset tracked by ArusGrid, including Racks Central Batam (RCBI). It sits on the Racks Central (Iskandar Halal Park). Named funding comes from China-ASEAN Fund II (CAF II, ESR-linked) on the equity side. No user of the capacity is on the public record as of 2026-10-02, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The build is phased. Phase A, RCJM1 (fully committed) at 70 MW is under construction with a 2027 target; RCJM2A at 175 MW is announced; RCJM2B at 175 MW is announced. The stage was recorded as under construction on 11 December 2025. Power comes from Tenaga Nasional Berhad (TNB) through grid supply. Cooling uses direct liquid cooling.

Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 30 June 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

liquid-ready GPU-focused (DCD)

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Phase A, RCJM1 (fully committed) · Under construction70 MW, target 2027
RCJM2A · Announced175 MW
RCJM2B · Announced175 MW

Stage history

2025-12-11Under construction · datacenterdynamics.com

Who is behind it

OperatorRacks Central (Singapore) · Colocation
Funder, EquityChina-ASEAN Fund II (CAF II, ESR-linked)

Who uses the compute

Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$677m to US$1.0bn

No figure has been announced. This range is 70 MW of planned IT load times a published benchmark of US$11.37 per watt for Malaysia, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Colocation price per kW of IT load per month

No colocation price applies to this product (retail interconnection, no colocation price applies).

Land
Industrial estateIskandar Halal Park · 5 acres · Oct 2024 Reported source ↗
Five-acre plot acquired October 2024. Seller not named.
Power supply
Grid supplyTenaga Nasional Berhad (TNB) · 100 MW · Apr 2026 Confirmed source ↗
MoUs with unnamed RE suppliers · ESA for first phase · Applies to the whole campus.
Water and cooling
WaterIndustrial raw water · Johor Special Water Reported source ↗
Johor Special Water named as supplier to RCJM 1 and RCJM 2A.
CoolingDirect liquid cooling Reported source ↗
Direct-to-chip cooling. Water drawn from Iskandar Reservoir and treated on site.

Sources checked 2026-10-21

  1. datacenterdynamics.com
  2. esr.com
  3. Racks Central Celebrates Milestone for Southeast Asia's First AI Factory Campus in Johor (Racks Central, 2026-06-30)
  4. Racks Central’s AIDC Phase 1 on track to open in 1Q 2027 (W.Media, 2026-06-30)

More in Johor

Also run by Racks Central

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.