Racks Central Batam (RCBI) data center

Batam, Riau Islands, Indonesia · Batam and Bintan market · location approximate to district level

Racks Central Batam (RCBI) is a data center project in Batam, Indonesia, operated by Racks Central. It is at the land and permitting stage. It is planned for 95 MW of IT load.

Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
95 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Racks Central
Colocation
AI workloads
Likely
Evidence grade
Sourced
Will it get built?Long shot0 of 7 gates passed
○ Land secured○ Power arranged○ Approvals granted○ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Land secured.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Indonesia approves, powers and taxes data centers is on Data center rules in Indonesia.

Where it sits

Batam and Bintan holds 12 active projects with 835 MW of planned IT load between them, and Racks Central Batam (RCBI) ranks 4th by planned capacity. Of those, 2 are operational, 4 are under construction, 2 are at the land and permitting stage and 4 are announced only. No third party publishes a colocation vacancy rate for Batam and Bintan, and ArusGrid does not estimate one.

Racks Central has 1 project elsewhere in the dataset tracked by ArusGrid, including Racks Central Johor Campus. It sits on the Nongsa Digital Park alongside BW Digital NDP1, DayOne Nongsa Digital Park Campus (NDP1-3), Golden Digital Gateway (Nongsa One) and Princeton Digital Group BT1. No user of the capacity is on the public record as of 2026-10-01, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

Grid power for a large industrial user in Indonesia costs about US$0.062 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Indonesia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 6 public sources for this project, the latest dated 21 August 2026, and last checked the record on 21 October 2026.

How well evidenced is it

One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Operator markets it as a 95MW liquid-ready greenfield for high-density AI/HPC and cloud workloads. Stated AI purpose + ≥100MW-class greenfield, but no tenant, no dated cooling spec, and no construction start.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Who is behind it

OperatorRacks Central · Colocation

Who uses the compute

Checked on 2026-10-01. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

ArusGrid estimate, building costabout US$905m to US$1.3bn

No figure has been announced. This range is 95 MW of planned IT load times a published benchmark of US$11.21 per watt for Jakarta, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Colocation price per kW of IT load per month

No colocation price applies to this product (retail interconnection, no colocation price applies).

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-10-21

  1. rackscentral.com
  2. datacentermap.com
  3. baxtel.com
  4. Racks Central builds regional AI data centre corridor across Singapore, Johor and Batam (Southeast Asia Infrastructure, 2026-01-21)
  5. Mapping Indonesia's Data Center Race: Early-Stage Growth with a Deep Pipeline (BRI Danareksa Sekuritas (BRIDS), 2026-08-21)
  6. ESR, CAF II fund invests in Racks Central; supports 510MW data centre campus in Johor, Malaysia (Structure Research, 2026-08-05)

Same campus, Nongsa Digital Park

More in Batam and Bintan

Also run by Racks Central

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.