Logos-UEM Sunrise Gerbang Nusajaya Campus

Iskandar Puteri (Gerbang Nusajaya), Johor, Malaysia · Johor market · location approximate to district level
Why it stopped. No reason published A 2023 MoU for a 30ha campus of up to 360MW was reported cancelled. No party published a reason. source The graveyard.

Logos-UEM Sunrise Gerbang Nusajaya Campus was a data center project in Iskandar Puteri (Gerbang Nusajaya), Malaysia, operated by Logos (ESR) + UEM Sunrise. It was cancelled. ArusGrid keeps it on record and excludes it from every total. It was planned for 360 MW of IT load.

Latest change on record: entered the record as cancelled in May 2025. Record last checked against its sources on 19 October 2026.

Open on the mapSuggest a correction
Stage
Cancelled
Planned IT load
360 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Logos (ESR) + UEM Sunrise
Joint venture
AI workloads
No signal either way
Evidence grade
None

Where it sits

Johor holds 43 active projects with 4,880 MW of planned IT load between them. Of those, 3 are operational, 9 are operational and expanding, 11 are under construction, 1 is past financial close, 5 are at the land and permitting stage and 14 are announced only. Published colocation vacancy in Johor was 0.7% as of June 2026, on 897 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

It is the only Logos (ESR) + UEM Sunrise project ArusGrid tracks. It sits on the Gerbang Nusajaya DC Campus. Named funding comes from ESR Group on the equity side. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The stage was recorded as cancelled in May 2025.

Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 25 June 2025, and last checked the record on 19 October 2026.

How well evidenced is it

Cancelled projects carry no evidence grade.

AI workloads

StatusNo signal either way

no cooling/density/tenant signal published

Stage history

2025-05Cancelled · businesstoday.com.my

Who is behind it

OperatorLogos (ESR) + UEM Sunrise · Joint venture
Funder, EquityESR Group

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Colocation price per kW of IT load per month

No colocation price applies to this product (cancelled).

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-10-19

  1. datacenterdynamics.com
  2. baxtel.com
  3. CGS Cuts UEM Sunrise's TP After DC Termination And Project Delay (Business Today, 2025-05-25)
  4. UEM Sunrise to sell 74-acre land after scrapped data center deal: Report (W.Media, 2025-06-25)

More in Johor

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.