ArusGridProject
Directory › Malaysia › Johor › Microsoft Nusa Cemerlang (Mukim Pulai)

Microsoft Nusa Cemerlang (Mukim Pulai) data center

Iskandar Puteri (Gelang Patah), Johor, Malaysia · Johor market · location approximate to district level

Microsoft Nusa Cemerlang (Mukim Pulai) is a data center project in Iskandar Puteri (Gelang Patah), Malaysia, operated by Microsoft. It is at the land and permitting stage. The operator has not published a capacity figure, and ArusGrid does not estimate one.

Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Land and permitting
Planned IT load
Not published
Running now
Not disclosed
Operators rarely publish this
Operator
Microsoft
Hyperscaler self-build
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Open question3 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.

Where it sits

Johor holds 43 active projects with 4,880 MW of planned IT load between them, and Microsoft Nusa Cemerlang (Mukim Pulai) has no published figure so it sits outside that ranking. Of those, 3 are operational, 9 are operational and expanding, 11 are under construction, 1 is past financial close, 5 are at the land and permitting stage and 14 are announced only. Published colocation vacancy in Johor was 0.7% as of June 2026, on 897 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Microsoft has 3 others in Malaysia and 10 projects elsewhere in the dataset tracked by ArusGrid, including Microsoft Eco Business Park I, Microsoft Eco Business Park VI and Microsoft Malaysia West Region (3 sites, Greater KL). It sits on the Microsoft Johor - NCIP campus. The named user of the compute is Microsoft (confirmed).

The money on record is RM567.4m (about US$125m) as of June 2025, the announced investment.

Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 5 public sources for this project, the latest dated 17 August 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Named funderNo
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

hyperscaler self-build land (post-2023 = AI-era design)

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectYes
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Who is behind it

OperatorMicrosoft · Hyperscaler self-build

Who uses the compute

Own use · hyperscalerMicrosoft · confirmed

Full site, 102,560 sqm in Mukim Pulai bought from Crescendo Corporation's Panoramic Industrial Development Sdn Bhd for RM132.47m · as of 2024-04-05

DCD reports Crescendo Corporation Berhad's Bursa-announced conditional sale of 102,560 sqm in the Pulai area to Microsoft Payments (Malaysia) Sdn Bhd for RM132,471,276, completion expected Q4 2024. Landlord filing names the Microsoft entity.

Source · Microsoft acquires land in Johor, Malaysia, for data center (DCD, 2024-04-05)

Money at this site

Announced investment, 2025-06RM567.4m (about US$125m)

The figure covers land only.

Platform deals that include it

Microsoft Malaysia program
Country programme, 2024-05
US$2.2bn

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

An own-use build. No colocation price applies.

Land
Land sellerCrescendo Corp Bhd · 2,620,000 sqft · RM315.17m (≈US$71m) · Nov 2023 Confirmed source ↗
Three vacant parcels, Nusa Cemerlang Industrial Park, Pulai; buyer Microsoft Payments (M) Sdn Bhd
Land sellerCrescendo Corp Bhd (Panoramic Industrial Development Sdn Bhd) · 1,100,000 sqft · RM132.47m (≈US$30m) · freehold · Apr 2024 Confirmed source ↗
Pulai; buyer Microsoft Payments (Malaysia) Sdn Bhd; RM120 psf
Land sellerCrescendo Corporation (Panoramic Industrial Development) · 22.548 acres · RM119.8m (≈US$27m) · Jan 2025 Confirmed source ↗
Nusa Cemerlang Industrial Park, Pulai; completion by 2Q2027; turned unconditional Jul 2026
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedSunway Construction Sdn Bhd · Main contractor · RM1.16bn (≈US$261m) · May 2025 source ↗
This project is one of 2 that fit. The other is Microsoft Eco Business Park VI.
UnconfirmedSunway Construction Sdn Bhd · Core and shell builder · RM570m (≈US$128m) · Dec 2025 source ↗
This project is one of 2 that fit. The other is Microsoft Eco Business Park VI.
UnconfirmedSunway Construction Sdn Bhd · Utility infrastructure · RM386m (≈US$87m) · Dec 2025 source ↗
This project is one of 2 that fit. The other is Microsoft Eco Business Park VI.
UnconfirmedSunway Construction Sdn Bhd · Grid and substation works · RM201.2m (≈US$45m) · Apr 2026 source ↗
This project is one of 2 that fit. The other is Microsoft Eco Business Park VI.
UnconfirmedSunway Construction Sdn Bhd · Grid and substation works · RM664.4m (≈US$150m) · Jun 2026 source ↗
This project is one of 2 that fit. The other is Microsoft Eco Business Park VI.
UnconfirmedSunway Construction Sdn Bhd · Mechanical and electrical works · RM1.02bn (≈US$230m) · Aug 2026 source ↗
This project is one of 2 that fit. The other is Microsoft Eco Business Park VI.
UnconfirmedJati Tinggi Holding Sdn Bhd · Grid and substation works · RM10.56m (≈US$2m) · Jul 2026 source ↗
This project is one of 3 that fit. The others are STACK JHB01, EdgeConneX Johor.
UnconfirmedSunway Construction Sdn Bhd · Mechanical and electrical works · RM1.02bn · Aug 2026 source ↗
This project is one of 3 that fit. The others are Microsoft Eco Business Park VI, Microsoft Eco Business Park I.
UnconfirmedSunway Construction Sdn Bhd · Core and shell builder · RM570m · Dec 2025 source ↗
This project is one of 3 that fit. The others are Microsoft Eco Business Park VI, Microsoft Eco Business Park I.
UnconfirmedMidtown Engineering Sdn Bhd · Mechanical and electrical works · RM63.6m · Dec 2025 source ↗
This project is one of 3 that fit. The others are Microsoft Eco Business Park VI, Microsoft Eco Business Park I.

Sources checked 2026-10-21

  1. forbes.com
  2. w.media
  3. datacentermap.com
  4. Microsoft details plans for cloud region in Johor, Malaysia (DCD, 2025-11-05)
  5. Land monetisation yields massive earnings gain (The Edge Malaysia, 2026-08-17)

More in Johor

Also run by Microsoft

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.