Tera Data Centers Port Dickson (Eco Business Park 7) is a data center project in Port Dickson (Mukim Jimah), Malaysia, operated by Tera Data Centers (Malaysia) Sdn Bhd. It has been announced and has not yet reached the land or permitting stage. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: entered the record as announced on 22 September 2026. Record last checked against its sources on 21 October 2026.
Next gate to watch: Power arranged.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.
Klang Valley holds 33 active projects with 1,911 MW of planned IT load between them, and Tera Data Centers Port Dickson (Eco Business Park 7) has no published figure so it sits outside that ranking. Of those, 5 are operational, 5 are operational and expanding, 10 are under construction, 7 are at the land and permitting stage and 6 are announced only. No third party publishes a colocation vacancy rate for Klang Valley, and ArusGrid does not estimate one.
It is the only Tera Data Centers project ArusGrid tracks. It sits on the Eco Business Park 7 (Malaysia Vision Valley 2.0). Named funding comes from HSG on the equity side. No user of the capacity is on the public record as of 2026-10-03, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.
The stage was recorded as announced only on 22 September 2026.
Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 26 September 2026, and last checked the record on 21 October 2026.
One or two hard signals sit behind the announcement. The rules are fixed and published on the Methodology page.
Operator states its campuses are built for AI; 221-acre greenfield site bought in 2026.
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-03. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
No published price band exists for Malaysia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Klang Valley · All projects in Malaysia · All projects announced only · Data center rules in Malaysia · Full directory