Digital Cosmos Cyberjaya is a data center project in Cyberjaya, Malaysia, operated by Digital Cosmos. It is at the land and permitting stage. The operator has not published a capacity figure, and ArusGrid does not estimate one.
Latest change on record: entered the record as land and permitting on 7 August 2026. Record last checked against its sources on 20 October 2026.
Next gate to watch: Land secured.
Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.
How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.
Klang Valley holds 33 active projects with 1,911 MW of planned IT load between them, and Digital Cosmos Cyberjaya has no published figure so it sits outside that ranking. Of those, 5 are operational, 5 are operational and expanding, 10 are under construction, 7 are at the land and permitting stage and 6 are announced only. No third party publishes a colocation vacancy rate for Klang Valley, and ArusGrid does not estimate one.
It is the only Digital Cosmos project ArusGrid tracks. Named funding comes from Digital Cosmos (S) Pte Ltd on the equity side. No user of the capacity is on the public record as of 2026-10-03, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.
The stage was recorded as at the land and permitting stage on 7 August 2026. The money on record is RM419.05m (about US$102m) as of August 2026, the announced investment.
Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 2 public sources for this project, the latest dated 7 August 2026, and last checked the record on 20 October 2026.
Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.
No tenant, workload or cooling disclosure. Sponsor is three months old with no operating history, so scale alone is not treated as a signal. 182MW modern greenfield campus (size rule).
This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.
No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source
Checked on 2026-10-03. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.
The figure covers land only.
No published price band exists for Malaysia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.
All projects in Klang Valley · All projects in Malaysia · All projects at the land and permitting stage · Data center rules in Malaysia · Full directory