ArusGridProject
Directory › Thailand › EEC (Eastern Seaboard) › CtrlS Datacenters EECd Hyperscale Campus (with National Telecom)

CtrlS Datacenters EECd Hyperscale Campus (with National Telecom)

Si Racha (EECd / Digital Park Thailand), Chonburi, Thailand · EEC (Eastern Seaboard) market · location approximate to district level
Why it stopped. No progress on record A 50-year land lease and a 2023 agreement were the last dated facts. No construction, financing, contractor or Board of Investment approval followed in the next three years. source The graveyard.

CtrlS Datacenters EECd Hyperscale Campus (with National Telecom) was a data center project in Si Racha (EECd / Digital Park Thailand), Thailand, operated by CtrlS Datacenters. It was cancelled. ArusGrid keeps it on record and excludes it from every total. It was planned for 150 MW of IT load.

Latest change on record: entered the record as cancelled on 28 August 2026. Record last checked against its sources on 11 September 2026.

Open on the mapSuggest a correction
Stage
Cancelled
Planned IT load
150 MW
Running now
Not disclosed
Operators rarely publish this
Operator
CtrlS Datacenters
Colocation
AI workloads
Likely
Evidence grade
None

Where it sits

EEC (Eastern Seaboard) holds 21 active projects with 3,703 MW of planned IT load between them. Of those, 2 are operational, 1 is operational and expanding, 9 are under construction, 7 are at the land and permitting stage and 2 are announced only. No third party publishes a colocation vacancy rate for EEC (Eastern Seaboard), and ArusGrid does not estimate one.

CtrlS has 5 projects elsewhere in the dataset tracked by ArusGrid, including CtrlS Chandanvelly datacenter park, CtrlS Mumbai datacenter campus (DC1 to DC7) and CtrlS Bodh Gaya AI Factory. Named funding comes from CtrlS Datacenters on the equity side and National Telecom (NT). No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The stage was recorded as cancelled on 28 August 2026. The money on record is THB 15bn (about US$429m) as of August 2023, the announced investment.

Grid power for a large industrial user in Thailand costs about US$0.10 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Thailand, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 4 public sources for this project, the latest dated 11 July 2023, and last checked the record on 11 September 2026.

How well evidenced is it

Cancelled projects carry no evidence grade.

AI workloads

StatusLikely

150MW greenfield hyperscale campus (>=100MW). CtrlS is a Rated-4 hyperscale operator; no Thailand-specific cooling or GPU spec published.

Stage history

2026-08-28Cancelled · datacenterdynamics.com

Who is behind it

OperatorCtrlS Datacenters · Colocation
Funder, EquityCtrlS Datacenters
Funder, Joint venture partnerNational Telecom (NT)

Who uses the compute

No tenant disclosed. Most colocation leases are confidential, so this says nothing about occupancy. Not yet checked against second-order sources.

Money at this site

Announced investment, 2023-08THB 15bn (about US$429m)

The figure covers the whole campus.

Colocation price per kW of IT load per month

No colocation price applies to this product (cancelled).

Build, land, power and water
Nothing found in public sources yet. Most contractors and utilities never name their data centre clients. Know who built it or where its power comes from? Tell us.

Sources checked 2026-09-11

  1. bangkokpost.com
  2. telecomreviewasia.com
  3. datacenterdynamics.com
  4. CtrlS to develop 150MW campus in Thailand (DatacenterDynamics, 2023-07-11)

More in EEC (Eastern Seaboard)

Also run by CtrlS

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.