MRCB / Perintis Akal AI Data Centre (Bukit Jalil)

Bukit Jalil, Kuala Lumpur, Malaysia · Klang Valley market · location approximate to district level

MRCB / Perintis Akal AI Data Centre (Bukit Jalil) is a data center project in Bukit Jalil, Malaysia, operated by Perintis Akal Sdn Bhd (PEMANDU Partners International). It has been announced and has not yet reached the land or permitting stage. It is planned for 65 MW of IT load.

Latest change on record: entered the record as announced in June 2026. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Announced
Planned IT load
65 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Perintis Akal Sdn Bhd (PEMANDU Partners International)
Local developer
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Open question2 of 7 gates passed
✓ Land secured○ Power arranged○ Approvals granted✓ Money committed○ Tenant or own use○ Builder appointed○ Construction started

Next gate to watch: Power arranged.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.

Where it sits

Klang Valley holds 33 active projects with 1,911 MW of planned IT load between them, and MRCB / Perintis Akal AI Data Centre (Bukit Jalil) ranks 8th by planned capacity. Of those, 5 are operational, 5 are operational and expanding, 10 are under construction, 7 are at the land and permitting stage and 6 are announced only. No third party publishes a colocation vacancy rate for Klang Valley, and ArusGrid does not estimate one.

It is the only Perintis Akal project ArusGrid tracks. It sits on the Bukit Jalil Sentral campus. Named funding comes from Malaysian Resources Corporation Berhad (MRCB). No user of the capacity is on the public record as of 2026-10-02, after a check of operator, landlord, contractor, regulator and lender documents. Most colocation leases are confidential, so this says nothing about occupancy.

The stage was recorded as announced only in June 2026. The money on record is RM2,100m (about US$494m) as of June 2026, the announced investment.

Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 6 public sources for this project, the latest dated 1 September 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed clientNo
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

Stated design for GPU-based AI workloads with high-density power and cooling; 65MW greenfield IT load, Uptime Tier III.

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Phase 1 · Announced65 MW, target 2027

Stage history

2026-06Announced · w.media

Who is behind it

OperatorPerintis Akal Sdn Bhd (PEMANDU Partners International) · Local developer
Funder, Joint venture partnerMalaysian Resources Corporation Berhad (MRCB)

Who uses the compute

Checked on 2026-10-02. No user of this capacity is on the public record. ArusGrid read the operator's releases, the landlord's and contractors' exchange filings, regulator and lender documents and interconnection records. Most colocation leases are confidential, so this says nothing about occupancy.

Money at this site

Announced investment, 2026-06RM2,100m (about US$494m)

Colocation price per kW of IT load per month

No published price band exists for Malaysia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Project team
Design and build contractorInspur Communication Malaysia Sdn Bhd · Jun 2026 · bid submitted, result pending Reported source ↗
Construction, commissioning, maintenance and operation, named in the collaboration agreement of 16 June 2026. Definitive agreements pending.
Land
LandlordBukit Jalil Sentral Property Sdn Bhd (MRCB Land) · 37,320 sqm · leased · Jun 2026 Reported source ↗
10-year lease to Perintis Akal Sdn Bhd
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedJati Tinggi Holding Sdn Bhd · Grid and substation works · RM6.59m (≈US$2m) · Sep 2024 source ↗
This project is one of 3 that fit. The others are Bridge Data Centres MY03, EdgeConneX Bukit Jalil.

Sources checked 2026-10-21

  1. thestar.com.my
  2. edgeprop.my
  3. MRCB 2Q profit slips 4% as construction revenue falls; BJSP gain lifts PBT (EdgeProp, 2026-09-01)
  4. MRCB eyes stronger growth on RM8.5bil order book (The Star, 2026-08-28)
  5. MRCB enters data center market with 65 MW project in Bukit Jalil, Malaysia (W.Media, 2026-06-25)
  6. MRCB unit signs collaboration agreement for RM2.1 bil AI-ready data centre facility in Bukit Jalil (EdgeProp, 2026-06-18)

More in Klang Valley

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.