Nxera DC Tuas

Singapore, Singapore · Singapore market

Nxera DC Tuas is a data center project in Singapore, operated by Nxera (Singtel). It is operational. It is planned for 58 MW of IT load. The operator reports 58 MW running.

Latest change on record: moved to operational on 9 February 2026. Record last checked against its sources on 21 October 2026.

Open on the mapSuggest a correction
Stage
Operational
Planned IT load
58 MW
Running now
58 MW
Operators rarely publish this
Operator
Nxera (Singtel)
Telco
AI workloads
Confirmed
Evidence grade
Verified
Will it get built?Built7 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use✓ Builder appointed✓ Construction started

This project is built or running, so every gate counts as passed.

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Singapore approves, powers and taxes data centers is on Data center rules in Singapore.

Where it sits

Singapore holds 39 active projects with 874 MW of planned IT load between them, and Nxera DC Tuas ranks 4th by planned capacity. Of those, 27 are operational, 3 are operational and expanding, 3 are under construction, 1 is past financial close and 5 are announced only. Published colocation vacancy in Singapore was 4.9% as of December 2025, on 1,043 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Nxera (Singtel) has 2 others in Singapore tracked by ArusGrid, including Nxera DC West and Nxera Kim Chuan 2. Named funding comes from Singtel and KKR on the equity side. No tenant has been disclosed, which is normal for colocation and says nothing about occupancy.

The dated record runs from under construction on 8 August 2023 to operational on 9 February 2026. The money on record is S$643m (about US$476m) as of February 2025, debt raised, which ArusGrid keeps out of capital totals. Power comes from Nxera through onsite solar. Cooling uses direct liquid cooling, with a design PUE of 1.25.

Grid power for a large industrial user in Singapore costs about US$0.20 per kWh as of July 2026, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Singapore, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 7 public sources for this project, the latest dated 10 February 2026, and last checked the record on 21 October 2026.

How well evidenced is it

Running capacity. The site is operational or expanding. The rules are fixed and published on the Methodology page.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalYes
Dated, sized phaseYes
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusConfirmed

SG's largest direct-to-chip liquid cooling deployment

Access to AI chips

GradeNo US licence required

This country carries no US destination-based licence requirement for advanced AI chips as the rules are enforced today. Access is a commercial matter between the project and its vendors. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectNo
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Phases

Full build · Operational58 MW, target 2026

Stage history

2023-08-08Under construction · nxera-dc.com
2026-02-09Operational · itnews.asia

Who is behind it

OperatorNxera (Singtel) · Telco
Funder, EquitySingtel
Funder, EquityKKR

Who uses the compute

Tenant · enterpriseUndisclosed (>90% pre-committed) · reported, unconfirmed

More than 90% of 58MW committed before launch · as of 2026-02-09

DCD and The Edge (via Yahoo) both carry Singtel's opening statement that over 90% of DC Tuas capacity was committed before launch; no customer is named and tenant type is not stated, so the hyperscaler label is ArusGrid's reading rather than the source's wording.

Source · Singtel's Nxera opens Singapore data center (DCD, 2026-02-09)

Source · Singtel's Nxera opens AI-ready data centre in Tuas (The Edge Singapore via Yahoo Finance, 2026-02-08)

Money at this site

Debt raised, 2025-02S$643m (about US$476m)

This is the size of a loan. ArusGrid excludes it from capital spending totals.

Platform deals that include it

KKR 20% stake in Nxera
Platform capital, 2023-09
US$800m

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

ArusGrid estimate, grade CUSD 261 to USD 373

ArusGrid estimate, grade C. Published band for this country. Priced on the hyperscale band, which already reflects anchor deals. No usable capex for this site. Electricity excluded in the band. An estimate, never a quote, computed by fixed rules published on the Colo prices page and never counted in any total.

market band, hyperscale (2024-12)USD 261 to USD 373 datacenterHawk for NTT DC REIT, 2025-07-07
Power supply
Grid supply Confirmed source ↗
Dual power feed, diverse incoming cable routes; PUE ~1.25
On-site solarNxera Confirmed source ↗
Rooftop solar; MW not stated
Water and cooling
WaterRainwater harvesting Reported source ↗
PUE 1.25 at full load; rainwater harvesting, condensate reuse, blowdown recovery (main supply not stated)
CoolingDirect liquid cooling · design PUE 1.25 Reported source ↗
Direct-to-chip liquid cooling, >30kW/rack, largest D2C deployment in SG
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedObayashi Singapore Pte Ltd · Main contractor source ↗
This project is one of 3 that fit. The others are Nxera DC West, Nxera Kim Chuan 2.

Sources checked 2026-10-21

  1. datacenterdynamics.com
  2. w.media
  3. Nxera opens Singapore's data centre promising highest power density, energy efficiency (Techgoondu, 2026-02-10)
  4. Singtel begins construction of Singapore’s highest power density, hyper-connected green data centre (Singtel, 2023-08-08)
  5. Singtel's Nxera opens 58MW data centre in Singapore (iTnews Asia, 2026-02-09)
  6. Nxera opens multi-tenanted data centre (JTC (republished Singtel release), 2026-02-09)
  7. Singtel secures S$643 million green loan for DC Tuas (Nxera (Singtel), 2025-02-07)

More in Singapore

Also run by Nxera (Singtel)

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.