Data center projects in NCR

India · India · dataset updated 2026-10-18

ArusGrid tracks 12 active data center projects in NCR, India, with 1,055 MW of planned IT load. Of these, 4 are operational, 2 are operational and expanding, 2 are under construction and 4 are announced only. Projects under construction or commissioning account for 260 MW and operational sites for 275 MW of planned capacity. Operators have disclosed 65 MW actually running, a figure most of them do not publish.

The largest project is AM Group AI compute hub, Jewar at 350 MW, announced only. The operators with the most planned capacity here are AM Group, founders of Greenko (350 MW across 1 project), Anant Raj (307 MW across 3 projects) and Yotta (209 MW across 3 projects). Published colocation vacancy in NCR was 44% as of June 2025. Vacancy excludes hyperscaler self-build.

The US export control position for advanced AI chips in India, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”.

Open the mapPipeline view

All projects largest planned capacity first

ProjectCityStagePlanned MWRunning MWOperatorAI
AM Group AI compute hub, JewarJewar (Yamuna Expressway)Announced350 *undisclosedAM Group (AM AI Labs)Likely
Anant Raj Cloud RaiRai, SonipatUnder construction200undisclosedAnant Raj CloudNo signal either way
Yotta D4Greater NoidaAnnounced120 *undisclosedYotta Data ServicesConfirmed
AdaniConneX NoidaNoidaExpanding60 *10AdaniConneXLikely
Yotta D2Greater NoidaUnder construction60undisclosedYotta Data ServicesConfirmed
Anant Raj Cloud PanchkulaPanchkulaOperational577Anant Raj CloudNo signal either way
NTT Noida 2 campusNoidaOperational5322NTT Global Data CentersConfirmed
Anant Raj Cloud ManesarManesarExpanding5021Anant Raj CloudLikely
Yotta D1Greater NoidaOperational29undisclosedYotta Data ServicesLikely
STT Noida 3NoidaAnnounced28undisclosedSTT GDC IndiaNo signal either way
Sify Noida 02NoidaOperational264.32Sify Infinit SpacesLikely
STT Noida 2NoidaAnnounced22undisclosedSTT GDC IndiaNo signal either way

Cities in this market

Other markets in India

Operators here with their own page

* marks a capacity figure whose source states a basis other than IT load. Planned MW is IT load unless marked. Running capacity is rarely published, so a missing figure means undisclosed. Cancelled projects are listed and excluded from every total. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. This page is generated from the dataset, so it cannot drift from the map.