Bridge Data Centres MY07

Ulu Tiram, Johor, Malaysia · Johor market · location approximate to district level

Bridge Data Centres MY07 is a data center project in Ulu Tiram, Malaysia, operated by Bridge Data Centres (Chindata/Bain). It is under construction. It is planned for 200 MW of IT load.

Record last checked against its sources on 22 October 2026.

Open on the mapSuggest a correction
Stage
Under construction
Planned IT load
200 MW
Running now
Not disclosed
Operators rarely publish this
Operator
Bridge Data Centres (Chindata/Bain)
Colocation
AI workloads
Likely
Evidence grade
Corroborated
Will it get built?Strong6 of 7 gates passed
✓ Land secured✓ Power arranged✓ Approvals granted✓ Money committed✓ Tenant or own use○ Builder appointed✓ Construction started

Next gate to watch: Builder appointed.

Your call. Will it be built?

Build odds is ArusGrid's reading of the public record, not a forecast, a rating or advice. It counts the gates this project has passed in public sources. Private progress does not show, a passed gate can be undone, and projects that pass every gate still stop. The method has not yet been tested against outcomes. How it works.

How Malaysia approves, powers and taxes data centers is on Data center rules in Malaysia.

Where it sits

Johor holds 43 active projects with 4,880 MW of planned IT load between them, and Bridge Data Centres MY07 ranks 9th by planned capacity. Of those, 3 are operational, 9 are operational and expanding, 11 are under construction, 1 is past financial close, 5 are at the land and permitting stage and 14 are announced only. Published colocation vacancy in Johor was 0.7% as of June 2026, on 897 MW of operational colocation capacity as counted by Cushman & Wakefield. Vacancy excludes hyperscaler self-build.

Bridge Data Centres has 5 others in Malaysia and 2 projects elsewhere in the dataset tracked by ArusGrid, including Bridge Data Centres MY06, Bridge Data Centres MY01/MY02 and Bridge Data Centres MY03. It sits on the BDC MY07 (Ulu Tiram/Plentong) campus. Named funding comes from Bain Capital on the equity side. The named user of the compute is ByteDance (reported, unconfirmed).

Power comes from Tenaga Nasional Berhad (TNB) through grid supply (reported, unconfirmed). Cooling uses reclaimed water from Johor Special Water / IWK (treated effluent from JB-Pelangi STP), BDC-operated Ulu Tiram water reclamation plant.

Grid power for a large industrial user in Malaysia costs about US$0.14 per kWh as of July 2025, the country figure ArusGrid applies where a site has no published rate. The US export control position for advanced AI chips in Malaysia, as of 27 September 2026, is recorded as “No US destination-based licence requirement as enforced”. ArusGrid holds 5 public sources for this project, the latest dated 11 August 2025, and last checked the record on 22 October 2026.

How well evidenced is it

Construction or financing is evidenced, or several independent signals agree. The rules are fixed and published on the Methodology page.

Reaching this stage requires a dated construction source, which corroborates the project on its own.

Named funderYes
Disclosed client (reported)Yes
Committed or approved capitalNo
Dated, sized phaseNo
Three or more sourcesYes
Dated source in the last 24 monthsYes

AI workloads

StatusLikely

ByteDance reported; 400MW grid ESA

Access to AI chips

GradeLicence required for a party

A party to this project (its operator, that operator's group, a funder, or a confirmed client) is headquartered in China or Macau or has an ultimate parent there. US rules require a licence for advanced AI chips destined to such entities wherever they are located. This describes the rule and says nothing about whether a licence was sought, granted or refused. Criteria are published on the Methodology page.

US licence required for this destination as enforcedNo
A party headquartered in China or Macau on the projectYes
Country-level export frameworkNo
A party named in a government authorisationNo
US approved operator or confirmed client on the projectNo
Named chip-vendor partnershipNo

No US destination-based licence requirement as enforced · No US destination-based licence requirement as enforced (2026-09-27) source

Who is behind it

OperatorBridge Data Centres (Chindata/Bain) · Colocation
Funder, EquityBain Capital
Funder, DebtBank syndicate ($2.8B loan, APAC portfolio)

Who uses the compute

Tenant · hyperscalerByteDance · reported, unconfirmed

Money at this site

ArusGrid estimate, building costabout US$1.9bn to US$2.9bn

No figure has been announced. This range is 200 MW of planned IT load times a published benchmark of US$11.37 per watt for Malaysia, plus or minus 15 percent, with 10 percent more at the top for liquid cooling because the project is AI-positioned. It covers the building and its mechanical and electrical plant. It excludes land, grid works, servers and fees.

Benchmark: Turner & Townsend Data Centre Construction Cost Index 2025, as reported by Data Storage Asia. An estimate is never added to any total on the site.

Platform deals that include it

ByteDance Malaysia cumulative commitment
Country programme, 2026-01
US$6.6bn

Platform capital spans several sites. It is never added to this project's own figure.

Colocation price per kW of IT load per month

No published price band exists for Malaysia, and ArusGrid does not estimate from the regional benchmark alone. What was searched is listed on the Colo prices page.

Power supply
Grid supplyTenaga Nasional Berhad (TNB) · 400 MW · Nov 2024 Reported source ↗
MY07 ESA, Ulu Tiram; via TNB Green Lane Pathway
Renewable power dealTNB Renewables Sdn Bhd · Nov 2024 Reported source ↗
CRESS Bilateral Energy Supply Contract Head of Terms; MW not stated · Heads of terms only, not a final BESC
Green tariffTenaga Nasional Berhad (TNB Renewables Sdn Bhd for green supply) · 400 MW · Jan 2025 Reported source ↗
Bilateral Energy Supply Contract heads of terms under the Corporate Renewable Energy Supply Scheme (CRESS), first partner under the framework. · MY07 Electricity Supply Agreement for the Ulu Tiram site.
Water and cooling
WaterRecycled wastewater · Johor Special Water / IWK (treated effluent from JB-Pelangi STP), BDC-operated Ulu Tiram water reclamation plant · 5 MLD Reported source ↗
MBR + RO plant producing since 2025-06-09; 4 MLD at start (w.media), 5 MLD now, expansion to 20 MLD planned; RO by Suntar International
WaterRecycled wastewater · Johor Special Water (treated effluent from IWK plants) Confirmed source ↗
The Johor Menteri Besar said Bridge Data Centres' site in the Ulu Tiram Industrial Area began producing reclaimed water on 9 June 2025. This is earlier than the Q4 2025 full operation date in the held August 2025 release.
Possibly linked
The source does not name the project, and more than one project we track fits. We show it on each of them and pin it to none.
UnconfirmedTenaga Nasional Berhad (TNB) · Grid supply · Mar 2024 source ↗
This project is one of 2 that fit. The other is Bridge Data Centres MY06.
UnconfirmedParagon Globe Bhd subsidiary (not named) · Piling and earthworks · RM45.16m · Sep 2026 source ↗
This project is one of 3 that fit. The others are EdgeConneX Johor, STACK JHB01.

Sources checked 2026-10-22

  1. mingtiandi.com
  2. datacenterdynamics.com
  3. bridgedatacentres.com
  4. Bridge Data Centres, TNB sign MY07 400MW deal and green energy partnership, boosting Malaysia as a digital hub (Digital News Asia, 2024-12-04)
  5. Johor First State To Adopt Tier 4 Data Centre Technology - Onn Hafiz (Bernama, 2025-08-11)

More in Johor

Also run by Bridge Data Centres

Planned MW is IT load, the power available to servers, unless marked otherwise. Running capacity is rarely published, so a missing figure means undisclosed. Definitions, sourcing standards and evidence rules are on the Methodology page. Data is CC BY-NC 4.0. Corrections go to corrections@arusgrid.com. Dataset updated 2026-10-18.